Doubtnut Promotions Sticky

A can do a piece of work in 4 days and B can complete the same work in 12 days. What is the number of days required to do the same work together?

A

2 days

B

3 days

C

4 days

D

5 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem of how many days A and B will take to complete the work together, we can follow these steps:

1. Determine the work done by A in one day:
- A can complete the work in 4 days. Therefore, the work done by A in one day is:
Work done by A in one day=14

2. Determine the work done by B in one day:
- B can complete the work in 12 days. Therefore, the work done by B in one day is:
Work done by B in one day=112

3. Calculate the combined work done by A and B in one day:
- When A and B work together, their combined work done in one day is:
Combined work=14+112
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 4 and 12 is 12. We can convert 14 to have a denominator of 12:
14=312
- Now we can add:
312+112=412
- Simplifying 412:
412=13

4. Determine the total number of days required to complete the work together:
- If A and B together complete 13 of the work in one day, then the total number of days required to complete the entire work is the reciprocal of 13:
Total days=113=3

Final Answer:
A and B together will take 3 days to complete the work.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B together can do a piece of work in 6 days . If A can alone do the work in 18 days then the number of days required for B to finsh the work is

    A10
    B12
    C9
    D15
  • Question 2 - Select One

    A can do a piece of work in 16 days and B can do the same work in 20 days. In how many days can they do the same work, working together?

    A819
    B989
    C889
    D918
  • Question 3 - Select One

    2 men and 7 boys can do a piece of work in 4 days . 4 men and 4 boys can do the same work in 3 days . Then the number of days a boys a boy take to complete the same job is .

    A50 days
    B60 days
    C30 days
    D55 days