Suneeta can embroider a saree in 15 days. Her sister-in-law Abha can do the job in 10 days. They start embroidering the saree together, but two days later Abha gives up the work and goes to her parents. In how many days will Suneeta finish the remaining work of embroidering the saree?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will calculate the work done by Suneeta and Abha, and then determine how long it will take Suneeta to finish the remaining work after Abha leaves.

Step 1: Calculate Suneeta's work rate
Suneeta can complete the work in 15 days. Therefore, her work rate is:
Suneeta's work rate=115 (saree per day)

Step 2: Calculate Abha's work rate
Abha can complete the work in 10 days. Therefore, her work rate is:
Abha's work rate=110 (saree per day)

Step 3: Calculate their combined work rate
When Suneeta and Abha work together, their combined work rate is:
Combined work rate=115+110
To add these fractions, we need a common denominator. The least common multiple (LCM) of 15 and 10 is 30. Thus, we convert the fractions:
115=230,110=330
Now, adding the two:
Combined work rate=230+330=530=16 (saree per day)

Step 4: Calculate work done in the first 2 days
In 2 days, the amount of work they can complete together is:
Work done in 2 days=2×16=26=13 (saree)

Step 5: Calculate the remaining work
The total work is considered as 1 saree. Therefore, the remaining work after 2 days is:
Remaining work=113=23 (saree)

Step 6: Calculate the time taken by Suneeta to finish the remaining work
Now, we need to find out how long it will take Suneeta to complete the remaining 23 of the saree. Let x be the number of days Suneeta takes to finish the remaining work. We can set up the equation:
Work done by Suneeta in x days=115×x=23
To find x, we rearrange the equation:
x=23×15=10

Final Answer
Suneeta will finish the remaining work in 10 days after Abha leaves.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions