Twelve men, working at 8 h a day, can do a piece of work in 18 days. In how many days can 24 men working at 6 h a day can do the same work?

A

12

B

16

C

20

D

30

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will use the concept of work done, which can be expressed as:

Work=Number of Men×Hours per Day×Number of Days

Step 1: Calculate the total work done by the first group of men.

Given:
- Number of men (M1) = 12
- Hours per day (T1) = 8
- Number of days (D1) = 18

Using the formula for work:

Total Work=M1×T1×D1

Substituting the values:

Total Work=12×8×18

Step 2: Calculate the total work.

Calculating the above expression:

12×8=96
96×18=1728

So, the total work is 1728 man-hours.

Step 3: Set up the equation for the second group of men.

Now, we need to find out how many days (D2) it will take for the second group of men to complete the same work.

Given:
- Number of men (M2) = 24
- Hours per day (T2) = 6
- Number of days (D2) = x (unknown)

Using the same work formula:

Total Work=M2×T2×D2

Substituting the known values:

1728=24×6×x

Step 4: Solve for x (the number of days).

First, calculate 24×6:

24×6=144

Now, substituting this back into the equation:

1728=144×x

To find x, divide both sides by 144:

x=1728144

Step 5: Calculate the value of x.

Calculating the division:

x=12

Conclusion:

Thus, it will take 12 days for 24 men working at 6 hours a day to complete the same work.

---

Updated on:18/9/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Sixteen men, working at 6 h a day, can do a piece of work in 15 days. In how many days can 18 men working at 10 h a day do the same work?

    A18
    B10
    C16
    D8
  • Sixteen men, working at 6 h a day, can do a piece of work in 15 days. In how many days can 18 men working at 10 h a day do the same work?

    A18
    B10
    C16
    D8
  • If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?

    A15521 days
    B1123 days
    C6916 days
    D415 days