Twelve men, working at a day, can do a piece of work in days. In how many days can men working at a day can do the same work?
The correct Answer is:A
To solve the problem step by step, we will use the concept of work done, which can be expressed as:
Work=Number of Men×Hours per Day×Number of Days
Step 1: Calculate the total work done by the first group of men.
Given:
- Number of men (M1) = 12
- Hours per day (T1) = 8
- Number of days (D1) = 18
Using the formula for work:
Total Work=M1×T1×D1
Substituting the values:
Total Work=12×8×18
Step 2: Calculate the total work.
Calculating the above expression:
12×8=96
96×18=1728
So, the total work is 1728 man-hours.
Step 3: Set up the equation for the second group of men.
Now, we need to find out how many days (D2) it will take for the second group of men to complete the same work.
Given:
- Number of men (M2) = 24
- Hours per day (T2) = 6
- Number of days (D2) = x (unknown)
Using the same work formula:
Total Work=M2×T2×D2
Substituting the known values:
1728=24×6×x
Step 4: Solve for x (the number of days).
First, calculate 24×6:
24×6=144
Now, substituting this back into the equation:
1728=144×x
To find x, divide both sides by 144:
x=1728144
Step 5: Calculate the value of x.
Calculating the division:
x=12
Conclusion:
Thus, it will take 12 days for 24 men working at 6 hours a day to complete the same work.
---
- Number of men (M1) = 12
- Hours per day (T1) = 8
- Number of days (D1) = 18
96×18=1728
- Number of men (M2) = 24
- Hours per day (T2) = 6
- Number of days (D2) = x (unknown)
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - RATIO AND ITS APPLICATIONSEXERCISE - ASSESSMENT TESTS (TEST 1)12videos
RATIO AND ITS APPLICATIONS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - NUMBER SYSTEMEXERCISE - ASSESSMENT TESTS24videos
NUMBER SYSTEM
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - Set theoryEXERCISE - ASSESSMENT TEST Test 212videos
Set theory
Similar Questions
Knowledge Check
- Question 1 - Select One
Sixteen men, working at 6 h a day, can do a piece of work in 15 days. In how many days can 18 men working at 10 h a day do the same work?
A18B10C16D8 - Question 2 - Select One
Sixteen men, working at 6 h a day, can do a piece of work in 15 days. In how many days can 18 men working at 10 h a day do the same work?
A18B10C16D8 - Question 3 - Select One
If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
A15521 daysB1123 daysC6916 daysD415 days
20 Men can do a piece of work in 25 days, in how many days will 10 men do it?
View SolutionIf 36 men can do a piece of work in 25 days, in how many days will 15 men do it?
View SolutionIf 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
View Solution8 men working for 9 hours a day can complete a piece of work in 20 days. In how many days can 7 men working for 10 hours a day complete the same piece of work?
View Solution10 men working 8 hours day can do a work in 30 days. In how many days will 12 men working 4 hours a day take do the same work?
View Solution