Doubtnut Promotions Sticky

Twenty two men can complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?

A

11

B

22

C

33

D

none of these

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we can follow these steps:

Step 1: Calculate the total work in man-days
Given that 22 men can complete the work in 17 days, we can calculate the total work in man-days.

Total Work=Number of Men×Number of Days=22 men×17 days=374 man-days

Step 2: Calculate the work done in 2 days
Next, we need to find out how much work is done by 22 men in 2 days.

Work Done in 2 Days=22 men×2 days=44 man-days

Step 3: Calculate the remaining work
Now, we can find out how much work is left after the first 2 days.

Remaining Work=Total WorkWork Done in 2 Days=374 man-days44 man-days=330 man-days

Step 4: Calculate the work that needs to be done in 10 days
We need to complete the remaining work in 10 days. Let x be the number of additional men needed. The total number of men working will be 22+x.

The equation for the work done in 10 days by 22+x men is:

(22+x) men×10 days=330 man-days

Step 5: Set up the equation
From the above, we can set up the equation:

10(22+x)=330

Step 6: Solve for x
Now, we can simplify and solve for x:

220+10x=330

Subtract 220 from both sides:

10x=330220
10x=110

Now, divide by 10:

x=11

Conclusion
Thus, the number of additional men that should be employed is 11.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Twenty two men can complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?

    A11
    B22
    C33
    Dnone of these
  • Question 2 - Select One

    Twenty two men cann complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?

    A11
    B22
    C33
    D44
  • Question 3 - Select One

    Twenty two men cann complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?

    A45
    B60
    C57
    D80