Twenty two men can complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?
11
22
33
none of these
The correct Answer is:A
To solve the problem step by step, we can follow these steps:
Step 1: Calculate the total work in man-days
Given that 22 men can complete the work in 17 days, we can calculate the total work in man-days.
Total Work=Number of Men×Number of Days=22 men×17 days=374 man-days
Step 2: Calculate the work done in 2 days
Next, we need to find out how much work is done by 22 men in 2 days.
Work Done in 2 Days=22 men×2 days=44 man-days
Step 3: Calculate the remaining work
Now, we can find out how much work is left after the first 2 days.
Remaining Work=Total Work−Work Done in 2 Days=374 man-days−44 man-days=330 man-days
Step 4: Calculate the work that needs to be done in 10 days
We need to complete the remaining work in 10 days. Let x be the number of additional men needed. The total number of men working will be 22+x.
The equation for the work done in 10 days by 22+x men is:
(22+x) men×10 days=330 man-days
Step 5: Set up the equation
From the above, we can set up the equation:
10(22+x)=330
Step 6: Solve for x
Now, we can simplify and solve for x:
220+10x=330
Subtract 220 from both sides:
10x=330−220
10x=110
Now, divide by 10:
x=11
Conclusion
Thus, the number of additional men that should be employed is 11.
---
Given that 22 men can complete the work in 17 days, we can calculate the total work in man-days.
Next, we need to find out how much work is done by 22 men in 2 days.
Now, we can find out how much work is left after the first 2 days.
We need to complete the remaining work in 10 days. Let x be the number of additional men needed. The total number of men working will be 22+x.
From the above, we can set up the equation:
Now, we can simplify and solve for x:
10x=110
Thus, the number of additional men that should be employed is 11.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - RATIO, PROPORTION AND VARIATIONEXERCISE - LEVEL 36videos
RATIO, PROPORTION AND VARIATION
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - RATIO, PROPORTION AND VARIATIONEXERCISE - EXAMPLE46videos
RATIO, PROPORTION AND VARIATION
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - RATIO, PROPORTION AND VARIATIONEXERCISE - LEVEL 135videos
RATIO, PROPORTION AND VARIATION
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - PROFIT AND LOSS DISCOUNT AND PARTNERSHIP EXERCISE - CONCEPT APPLICATION (LEVEL 2)29videos
PROFIT AND LOSS DISCOUNT AND PARTNERSHIP
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - REAL NUMBERS AND LCM AND HCF EXERCISE - level -111videos
REAL NUMBERS AND LCM AND HCF
Similar Questions
Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionFifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View Solution
Knowledge Check
- Question 1 - Select One
Twenty two men can complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?
A11B22C33Dnone of these - Question 2 - Select One
Twenty two men cann complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?
A11B22C33D44 - Question 3 - Select One
Twenty two men cann complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?
A45B60C57D80
Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionTwenty five men can make a certain number of chairs in 80 working hours. They work for 10 hours. How many more men should now be employed so as to complete the work in another 50 working hours?
View SolutionTwenty five men can make a certain number of chairs in 80 working hours. They work for 10 hours. How many more men should now be employed so as to complete the work in another 50 working hours?
View Solution20 men complete one- third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days? 10 b. 12 c. 15 d. 20
View Solution45 men can complete a piece of work in 12 days. In how many days will 36 men be able to complete it?
View Solution