Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
The correct Answer is:16
To solve the problem step by step, we will use the formula related to work, which states:
M1×N1×D1×H1=M2×N2×D2×H2
Where:
- M = Number of men
- N = Number of days
- D = Number of hours per day
- H = Work done
Step 1: Determine the total work done by the initial group of men.
Given:
- 15 men can complete the work in 10 days, working 8 hours per day.
Total work W1 can be calculated as:
W1=M1×N1×D1×H1=15×10×8
Step 2: Calculate the total work W1.
W1=15×10×8=1200 man-hours
Step 3: Since we need to complete double the work, calculate W2.
W2=2×W1=2×1200=2400 man-hours
Step 4: Set up the equation for the second scenario.
We need to find the number of men M2 required to complete W2 in 25 days working 6 hours per day.
Using the formula:
M1×N1×D1×H1=M2×N2×D2×H2
Substituting the known values:
15×10×8×2=M2×25×6
Step 5: Substitute W2 into the equation.
2400=M2×25×6
Step 6: Solve for M2.
M2=240025×6
Step 7: Calculate M2.
M2=2400150=16
Conclusion:
Thus, 16 persons are required to complete double the work in 25 days, working 6 hours per day.
---
- M = Number of men
- N = Number of days
- D = Number of hours per day
- H = Work done
Given:
- 15 men can complete the work in 10 days, working 8 hours per day.
W1=M1×N1×D1×H1=15×10×8
W1=15×10×8=1200 man-hours
W2=2×W1=2×1200=2400 man-hours
We need to find the number of men M2 required to complete W2 in 25 days working 6 hours per day.
Using the formula:
M1×N1×D1×H1=M2×N2×D2×H2
Substituting the known values:
15×10×8×2=M2×25×6
2400=M2×25×6
M2=240025×6
M2=2400150=16
Thus, 16 persons are required to complete double the work in 25 days, working 6 hours per day.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-1)33videos
TIME AND WORK PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-2)20videos
TIME AND WORK PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - Short Answer Type Questions15videos
TIME AND WORK PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND DISTANCE EXERCISE - Concept Application (Level 2 )3videos
TIME AND DISTANCE
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)7videos
TIME AND WORK, PIPES AND CISTERNS
Similar Questions
Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionIf 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days?
View Solution
Knowledge Check
- Question 1 - Select One
7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?
A28B21C14D7 - Question 2 - Select One
7 men can complete a plece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?
A28B21C14D7 - Question 3 - Select One
18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?
A25B15C20D9
12 men can complete a work in 30 days by working 9 hours a day. What is the number of men required to complete 10 times of this work in 24 days by working 5 hours a day ?
View Solution18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?
View Solution7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work
View Solution30 persons can complete a work in 10 days. If they work 4 hours per day, then in how many days 45 persons can complete double the work if they work 8 hours per day? It is known that 2 persons of first type can do the same work in 2 hours that can be completed by 4 persons of 2nd type in 1 hour.
View SolutionIf 20 men take 15 days to complete a certain amount of work working at 10 hours per day, then how many more men are required to complete twice the previous work in 10 days working at 12 hours a day?
View Solution