Twenty two men cann complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?
A
45
B
60
C
57
D
80
Video Solution
Text Solution
The correct Answer is:A
(i) Apply m1d1=m2d2
(ii) Work done by 90 men in 15 days=Work done by (90+x) men in 10 days. ltBrgt i.e., 90×15=(90+x)10
|
Updated on:21/07/2023
Related Playlists
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - RATIO, PROPORTION AND VARIATIONEXERCISE - LEVEL 36videos
RATIO, PROPORTION AND VARIATION
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - RATIO, PROPORTION AND VARIATIONEXERCISE - EXAMPLE46videos
RATIO, PROPORTION AND VARIATION
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - RATIO, PROPORTION AND VARIATIONEXERCISE - LEVEL 135videos
RATIO, PROPORTION AND VARIATION
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - PROFIT AND LOSS DISCOUNT AND PARTNERSHIP EXERCISE - CONCEPT APPLICATION (LEVEL 2)29videos
PROFIT AND LOSS DISCOUNT AND PARTNERSHIP
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - REAL NUMBERS AND LCM AND HCF EXERCISE - level -111videos
REAL NUMBERS AND LCM AND HCF
Knowledge Check
- Question 1 - Select One
Twenty two men cann complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?
A11B22C33D44 - Question 1 - Select One
Twenty two men cann complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?
A45B60C57D80 - Question 1 - Select One
Twenty five men can make a certain number of chairs in 80 working hours. They work for 10 hours. How many more men should now be employed so as to complete the work in another 50 working hours?
A35B25C20D10 - Question 1 - Select One
Twenty five men can make a certain number of chairs in 80 working hours. They work for 10 hours. How many more men should now be employed so as to complete the work in another 50 working hours?
A35B25C20D10 - Question 1 - Select One
20 men complete one- third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days? 10 b. 12 c. 15 d. 20
A10B12C15D20 - Question 1 - Select One
40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?
A12B20C18D24 - Question 1 - Select One
15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
A40B42C38D32
Similar Questions
Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionFifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionFifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View Solution