Doubtnut Promotions Sticky

Two men and 7 children complete a certain piece of work in 4 days while 4 men and 4 children complete the same work in only 3 days. The number of days required by 1 man to complete the work is

A

60 days

B

15 days

C

6 days

D

51 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we need to determine how many days it takes for one man to complete a certain piece of work based on the information given about men and children working together.

1. Define Variables:
- Let m be the amount of work done by one man in one day.
- Let c be the amount of work done by one child in one day.

2. Work Done by Two Men and Seven Children:
- The work done by two men in one day is 2m.
- The work done by seven children in one day is 7c.
- Therefore, the total work done by two men and seven children in one day is:
2m+7c
- Since they complete the work in 4 days, the total work W can be expressed as:
W=4(2m+7c)=8m+28c

3. Work Done by Four Men and Four Children:
- The work done by four men in one day is 4m.
- The work done by four children in one day is 4c.
- Therefore, the total work done by four men and four children in one day is:
4m+4c
- Since they complete the work in 3 days, the total work W can also be expressed as:
W=3(4m+4c)=12m+12c

4. Setting the Two Expressions for Total Work Equal:
- Since both expressions represent the same total work W, we can set them equal to each other:
8m+28c=12m+12c

5. Rearranging the Equation:
- Rearranging gives:
28c12c=12m8m
16c=4m
- Dividing both sides by 4:
4c=m
- This means that one man does the work of four children in one day.

6. Finding Total Work in Terms of One Man's Work:
- We can substitute m=4c back into one of the expressions for W. Using W=8m+28c:
W=8(4c)+28c=32c+28c=60c

7. Finding the Number of Days for One Man to Complete the Work:
- If one man does m work in one day, then the number of days x required by one man to complete the work W is given by:
W=xm
- Substituting W=60c and m=4c:
60c=x4c
- Dividing both sides by 4c:
x=60c4c=15

Conclusion:
The number of days required by one man to complete the work is 15 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :

    A32 men
    B30 men
    C35 men
    D36 men
  • Question 2 - Select One

    2 men and 7 boys can do a piece of work in 4 days . 4 men and 4 boys can do the same work in 3 days . Then the number of days a boys a boy take to complete the same job is .

    A50 days
    B60 days
    C30 days
    D55 days
  • Question 3 - Select One

    12 men can complete a piece of work in 16 days. In how many days will 4 men complete the same piece of work?

    A60 days
    B45 days
    C54 days
    D48 days