Two men and 7 children complete a certain piece of work in 4 days while 4 men and 4 children complete the same work in only 3 days. The number of days required by 1 man to complete the work is
60 days
15 days
6 days
51 days
The correct Answer is:B
To solve the problem, we need to determine how many days it takes for one man to complete a certain piece of work based on the information given about men and children working together.
1. Define Variables:
- Let m be the amount of work done by one man in one day.
- Let c be the amount of work done by one child in one day.
2. Work Done by Two Men and Seven Children:
- The work done by two men in one day is 2m.
- The work done by seven children in one day is 7c.
- Therefore, the total work done by two men and seven children in one day is:
2m+7c
- Since they complete the work in 4 days, the total work W can be expressed as:
W=4(2m+7c)=8m+28c
3. Work Done by Four Men and Four Children:
- The work done by four men in one day is 4m.
- The work done by four children in one day is 4c.
- Therefore, the total work done by four men and four children in one day is:
4m+4c
- Since they complete the work in 3 days, the total work W can also be expressed as:
W=3(4m+4c)=12m+12c
4. Setting the Two Expressions for Total Work Equal:
- Since both expressions represent the same total work W, we can set them equal to each other:
8m+28c=12m+12c
5. Rearranging the Equation:
- Rearranging gives:
28c−12c=12m−8m
16c=4m
- Dividing both sides by 4:
4c=m
- This means that one man does the work of four children in one day.
6. Finding Total Work in Terms of One Man's Work:
- We can substitute m=4c back into one of the expressions for W. Using W=8m+28c:
W=8(4c)+28c=32c+28c=60c
7. Finding the Number of Days for One Man to Complete the Work:
- If one man does m work in one day, then the number of days x required by one man to complete the work W is given by:
W=x⋅m
- Substituting W=60c and m=4c:
60c=x⋅4c
- Dividing both sides by 4c:
x=60c4c=15
Conclusion:
The number of days required by one man to complete the work is 15 days.
- Let m be the amount of work done by one man in one day.
- Let c be the amount of work done by one child in one day.
- The work done by two men in one day is 2m.
- The work done by seven children in one day is 7c.
- Therefore, the total work done by two men and seven children in one day is:
2m+7c
- Since they complete the work in 4 days, the total work W can be expressed as:
W=4(2m+7c)=8m+28c
- The work done by four men in one day is 4m.
- The work done by four children in one day is 4c.
- Therefore, the total work done by four men and four children in one day is:
4m+4c
- Since they complete the work in 3 days, the total work W can also be expressed as:
W=3(4m+4c)=12m+12c
- Since both expressions represent the same total work W, we can set them equal to each other:
8m+28c=12m+12c
- Rearranging gives:
28c−12c=12m−8m
16c=4m
- Dividing both sides by 4:
4c=m
- This means that one man does the work of four children in one day.
- We can substitute m=4c back into one of the expressions for W. Using W=8m+28c:
W=8(4c)+28c=32c+28c=60c
- If one man does m work in one day, then the number of days x required by one man to complete the work W is given by:
W=x⋅m
- Substituting W=60c and m=4c:
60c=x⋅4c
- Dividing both sides by 4c:
x=60c4c=15
The number of days required by one man to complete the work is 15 days.
Topper's Solved these Questions
- BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - SIMULTANEOUS LINEAR EQUATIONSEXERCISE - SELF ASSESSMENT SHEET10videos
SIMULTANEOUS LINEAR EQUATIONS
- BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - SIMULTANEOUS LINEAR EQUATIONSEXERCISE - SELF ASSESSMENT SHEET10videos
SIMULTANEOUS LINEAR EQUATIONS
- BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - SIMPLE INTERESTEXERCISE - SELF ASSESSMENT SHEET-185videos
SIMPLE INTEREST
- BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - SOME APPLICATIONS OF TRIGONOMETRYEXERCISE - Unit Test - 620videos
SOME APPLICATIONS OF TRIGONOMETRY
Similar Questions
Knowledge Check
- Question 1 - Select One
24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
A32 menB30 menC35 menD36 men - Question 2 - Select One
2 men and 7 boys can do a piece of work in 4 days . 4 men and 4 boys can do the same work in 3 days . Then the number of days a boys a boy take to complete the same job is .
A50 daysB60 daysC30 daysD55 days - Question 3 - Select One
12 men can complete a piece of work in 16 days. In how many days will 4 men complete the same piece of work?
A60 daysB45 daysC54 daysD48 days
If 40 men complete a piece of work in 5 days, then 80 men can complete the same piece of work in _________.
View SolutionIf 12 men and 16 boys can complete a piece of work in 5 days and 13 men and 24 boys can complete the same work in 4 days, then in how many days 7 men and 10 boys will complete this work?
View Solution21 men can complete a piece of work in 427 days. In how many days can 18 men complete the same piece of work?
View SolutionIf 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?
View Solution24 boys can complete a work in 12 days while 16 men can complete the same work in 9 days. In how many days will 12 boys and 12 men together complete the same work ?
View Solution