Doubtnut Promotions Sticky

If 12 men and 16 boys can complete a piece of work in 5 days and 13 men and 24 boys can complete the same work in 4 days, then in how many days 7 men and 10 boys will complete this work?

A

8 days

B

9 days

C

813 days

D

1013 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we need to determine the amount of work done by men and boys, and then find out how long it will take for 7 men and 10 boys to complete the same work.

Step 1: Define the work done by men and boys
Let the work done by 1 man in 1 day be M and the work done by 1 boy in 1 day be B.

Step 2: Set up the equations based on the given information
From the first scenario:
- 12 men and 16 boys can complete the work in 5 days.
- Therefore, the total work can be expressed as:
5×(12M+16B)=W(1)

From the second scenario:
- 13 men and 24 boys can complete the work in 4 days.
- Therefore, the total work can be expressed as:
4×(13M+24B)=W(2)

Step 3: Equate the two expressions for work
Since both expressions equal the total work W, we can set them equal to each other:
5(12M+16B)=4(13M+24B)

Step 4: Expand both sides
Expanding both sides gives:
60M+80B=52M+96B

Step 5: Rearrange the equation
Rearranging the equation to isolate terms gives:
60M52M=96B80B
8M=16B

Step 6: Simplify the relationship between men and boys
Dividing both sides by 8 gives:
M=2B
This means that 1 man is equivalent to the work done by 2 boys.

Step 7: Substitute M in terms of B
Now, we can substitute M in terms of B into either equation (1) or (2). Let's use equation (1):
W=5×(12(2B)+16B)=5×(24B+16B)=5×40B=200B
So, the total work W is 200B.

Step 8: Calculate the work done by 7 men and 10 boys
Now, we need to find out how many days x it will take for 7 men and 10 boys to complete the work:
W=x×(7M+10B)
Substituting M=2B:
W=x×(7(2B)+10B)=x×(14B+10B)=x×24B

Step 9: Set the equation for total work
Now, we know W=200B:
200B=x×24B

Step 10: Solve for x
Dividing both sides by B (assuming B0):
200=24x
x=20024=2538.33

Step 11: Convert to mixed number
Converting 253 to a mixed number gives:
813

Final Answer
Thus, 7 men and 10 boys will complete the work in 8 13 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    18 men or 25 boys can complete a work in 25 days. How many days will 36 men and 10 boys take to complete the work?

    A112/17
    B125/12
    C115/12
    D125/17
  • Question 2 - Select One

    18 men or 25 boys can complete a work in 25 days. How many days will 36 men and 10 boys take to complete the work?

    A112/17
    B125/12
    C115/12
    D125/17
  • Question 3 - Select One

    6 men or 10 boys can complete a piece of work in 15 days. If 7 men and x boys complete the same piece of work in 9 days, then x is equal to

    A4
    B5
    C6
    D7