If 12 men and 16 boys can complete a piece of work in 5 days and 13 men and 24 boys can complete the same work in 4 days, then in how many days 7 men and 10 boys will complete this work?
8 days
9 days
813 days
1013 days
The correct Answer is:C
To solve the problem step by step, we need to determine the amount of work done by men and boys, and then find out how long it will take for 7 men and 10 boys to complete the same work.
Step 1: Define the work done by men and boys
Let the work done by 1 man in 1 day be M and the work done by 1 boy in 1 day be B.
Step 2: Set up the equations based on the given information
From the first scenario:
- 12 men and 16 boys can complete the work in 5 days.
- Therefore, the total work can be expressed as:
5×(12M+16B)=W(1)
From the second scenario:
- 13 men and 24 boys can complete the work in 4 days.
- Therefore, the total work can be expressed as:
4×(13M+24B)=W(2)
Step 3: Equate the two expressions for work
Since both expressions equal the total work W, we can set them equal to each other:
5(12M+16B)=4(13M+24B)
Step 4: Expand both sides
Expanding both sides gives:
60M+80B=52M+96B
Step 5: Rearrange the equation
Rearranging the equation to isolate terms gives:
60M−52M=96B−80B
8M=16B
Step 6: Simplify the relationship between men and boys
Dividing both sides by 8 gives:
M=2B
This means that 1 man is equivalent to the work done by 2 boys.
Step 7: Substitute M in terms of B
Now, we can substitute M in terms of B into either equation (1) or (2). Let's use equation (1):
W=5×(12(2B)+16B)=5×(24B+16B)=5×40B=200B
So, the total work W is 200B.
Step 8: Calculate the work done by 7 men and 10 boys
Now, we need to find out how many days x it will take for 7 men and 10 boys to complete the work:
W=x×(7M+10B)
Substituting M=2B:
W=x×(7(2B)+10B)=x×(14B+10B)=x×24B
Step 9: Set the equation for total work
Now, we know W=200B:
200B=x×24B
Step 10: Solve for x
Dividing both sides by B (assuming B≠0):
200=24x
x=20024=253≈8.33
Step 11: Convert to mixed number
Converting 253 to a mixed number gives:
813
Final Answer
Thus, 7 men and 10 boys will complete the work in 8 13 days.
Let the work done by 1 man in 1 day be M and the work done by 1 boy in 1 day be B.
From the first scenario:
- 12 men and 16 boys can complete the work in 5 days.
- Therefore, the total work can be expressed as:
5×(12M+16B)=W(1)
- 13 men and 24 boys can complete the work in 4 days.
- Therefore, the total work can be expressed as:
4×(13M+24B)=W(2)
Since both expressions equal the total work W, we can set them equal to each other:
5(12M+16B)=4(13M+24B)
Expanding both sides gives:
60M+80B=52M+96B
Rearranging the equation to isolate terms gives:
60M−52M=96B−80B
8M=16B
Dividing both sides by 8 gives:
M=2B
This means that 1 man is equivalent to the work done by 2 boys.
Now, we can substitute M in terms of B into either equation (1) or (2). Let's use equation (1):
W=5×(12(2B)+16B)=5×(24B+16B)=5×40B=200B
So, the total work W is 200B.
Now, we need to find out how many days x it will take for 7 men and 10 boys to complete the work:
W=x×(7M+10B)
Substituting M=2B:
W=x×(7(2B)+10B)=x×(14B+10B)=x×24B
Now, we know W=200B:
200B=x×24B
Dividing both sides by B (assuming B≠0):
200=24x
x=20024=253≈8.33
Converting 253 to a mixed number gives:
813
Thus, 7 men and 10 boys will complete the work in 8 13 days.
Topper's Solved these Questions
Similar Questions
12 men and 16 boys can do a piece of work in 5 days. 13 men and 24 boys can do the same work in 4 days. How long will 7 men and 10 boys take to do the same work?
View Solution2 men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 8 days. In how many days can 2 men and 1 boy do the work?
View Solution
Knowledge Check
- Question 1 - Select One
18 men or 25 boys can complete a work in 25 days. How many days will 36 men and 10 boys take to complete the work?
A112/17B125/12C115/12D125/17 - Question 2 - Select One
18 men or 25 boys can complete a work in 25 days. How many days will 36 men and 10 boys take to complete the work?
A112/17B125/12C115/12D125/17 - Question 3 - Select One
6 men or 10 boys can complete a piece of work in 15 days. If 7 men and x boys complete the same piece of work in 9 days, then x is equal to
A4B5C6D7
If 9 men and 12 boys can do a piece of work in 4 days and 4 men and 16 boys can do the
same work in 6 days, how long will 6 men and 24 boys take to complete the same work?View Solution2 men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 8 days. In how many days can 2 men and 1 boy do the same work ?
View SolutionIf 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can complete the work in 2 days then in how many days the work will be completed by 15 men and 20 boys?
View SolutionIf 3 men and 4 boys can do a piece of work in 8 day, then 6 men and 8 boys can do the same work in
View Solution12 men or 30 boys can complete a work in 72 days. How many days will 48 men and 24 boys will take to complete the same work?
View Solution