Doubtnut Promotions Sticky

Complete Solutions to Question Bank - 20 (a) of chapter TIME AND WORK of Class 8 book with complete answers and questions

Class 8MATHS
ChapterTIME AND WORK
S CHAND IIT JEE FOUNDATIONQuestion Bank - 20 (a)
Number Of Questions27
Academic Year2023-24
  1. A can do `1/5` th part of the work in 12 days, B can do 60% of the work in 30 days and C can do `1/3` rd of the work in 15 days. Who will complete the work first?


    02:15
    View Solution
  2. Ten women can complete a picce of work in 15 days. Six men can complete the same piece of work in 10 days. In how many days can 5 women and six men together complete the piece of work?


    03:53
    View Solution
  3. 6 men or 10 boys can complete a piece of work in 15 days. If 7 men and x boys complete the same piece of work in 9 days, then x is equal to


    03:16
    View Solution
  4. Ramu can complete a job in 8 days. Shyamu can complete the same job in 12 days. However, Monu `3/4` th of the same job. Ramu works for 2 days and then leaves the job. The number of days that will be taken by Shyamu and Monu to complete the balance together is


    04:07
    View Solution
  5. If Ajit can do `1/4` of the work in 3 days and Sujit can `1/6` do of the same work in 4 days, how much will Ajit get if both work together and are paid ₹ 180 in all ?


    03:51
    View Solution
  6. The work done by a man, a woman and a child are in the ratio 3:2:1. If the daily wages of 20 men, 30 women and 36 children amount to ₹ 78, what will be the wages of 15 men, 21 women and 30 children for 18 weeks?


    06:31
    View Solution
  7. 40 men can do a piece of work in a given time. If only 30 men be engaged, 6 more days are needed to complete the work. In how many days can 60 men do the work?


    03:23
    View Solution
  8. A man and a boy working together can complete a work in 24 days. If for the last 6 days, the man alone does the work, then it is completed in 26 days. How long will the boy take to complete the work alone ?


    02:58
    View Solution
  9. A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?


    04:12
    View Solution
  10. A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave ?


    02:47
    View Solution
  11. A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for ₹ 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?


    02:27
    View Solution
  12. If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?


    03:37
    View Solution
  13. 12 cows together eat 756 kg of grass in 7 days. How much grass will be caten by 15 cows in 10 days?


    03:42
    View Solution
  14. If 5 spiders can catch 5 flies in 5 minutes, how many flies can 100 spiders catch in 100 minutes ?


    02:42
    View Solution
  15. 8 men working for 9 hours a day can complete a piece of work in 20 days. In how many days can 7 men working for 10 hours a day complete the same piece of work?


    04:14
    View Solution
  16. A job can be completed by 12 men in 12 days. How many extra days will be needed to complete the job, if 6 men leave after working for 6 days?


    03:15
    View Solution
  17. A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?


    04:31
    View Solution
  18. A wall of 100 metres can be built by 7 men or 10 women in 10 days. How many days will 14 men and 20 women take to build a wall of 600 metres ?


    04:12
    View Solution
  19. Twenty four men can complete a work in sixteen days. Thirty two women can complete the same work in twenty four days. Sixteen men and sixteen women started working and worked for 12 days. How many more. men are to be added to complete the remaining work in 2 days ?


    04:53
    View Solution
  20. 12 men and 16 boys can do a piece of work in 5 days, 13 men and 24 boys can do it in 4 days. The ratio of the daily work done by a man to that of a boy is


    04:33
    View Solution
  21. Three men four women and six children can complete a work in seven days. A woman dos double the work a man does and a child does half the work a man doe. How many women alone can complete this work in 7 days? `7` b. `8` c. `12` d. cannot be determined e. none of these


    02:10
    View Solution
  22. A man a wma and a boy can complete a job in 3,4, and 12 days respectively. How many boys must assist 1 man and 1 woman to complete the job in `1/4` of a day? `1` b. `\ 4` c. `19` d. `41`


    02:01
    View Solution
  23. A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. Al the machine are started at 9 a.m. while machine P is closed at 11 a.m. and the remaining two machines complete the work. Approximately at what time will the work be finished? `11 : 30\ adotmdot` b. `\ 12\ noon` c. `12 : 30\ pdotmdot` d. `1\ pdotmdot`


    03:00
    View Solution
  24. A takes 5 hours more time than that taken by B to complete a work. If working together they can complete a work in 6 hours, then the number of hours that takes to complete the work individually is


    03:12
    View Solution
  25. If `x` men, working `x` hours per day, can do `x` units of work in `x` days, then `y` mens, working `y` hours per day would be able to complete how many units of work in `y` days? `(x^2)/(y^3)` b. `(x^3)/(y^2)\ ` c. `(x^3)/(y^2)` d. `(y^3)/(x^2)`


    03:58
    View Solution
  26. A started a work and left after working for 2 days. Then B was called and he finished the work in 9 days. Had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working , alone, finish the whole work? `2. d a y s ,\ 7. 5\ d a y s` b. `5\ d a y s ,\ 8. 5\ d a y s` c. `5\ d a y s ,\ 15\ d a y s` d. none of these


    02:29
    View Solution
  27. 15 men can complete a work in 210 days. They started the work but at the end of 10 days, 15 additional men, with double efficiency, were in- ducted. How many days in all did they take to finish the work ?


    04:29
    View Solution

Question Bank - 20 (a) questions and complete solutions for chapter TIME AND WORK of S CHAND IIT JEE FOUNDATION of Class 8

All Exercises from S CHAND IIT JEE FOUNDATION Class 8 MATHS TIME AND WORK