Question

A job can be completed by 12 men in 12 days. How many extra days will be needed to complete the job if 6 men leave after working for 6 days ? a 3 days b 6 days c 12 days d 24 days

Text Solution
Verified by Experts

Correct option b 6 days Explanation:According to Question  Total work = 12M×12D=144 units Work done by 12 men in 6 days = 12 × 6 = 72 units Best work = 144 – 72 = 72 units Required time for 6 men to complete the work = 72/6 = 12Hence Total time = 12 + 6 = 18 days Extra time = 18 – 12 = 6 days


Related Solutions