A job can be completed by 12 men in 12 days. How many extra days will be needed to complete the job if 6 men leave after working for 6 days ? a 3 days b 6 days c 12 days d 24 days
Correct option b 6 days Explanation:According to Question Total work = 12M×12D=144 units Work done by 12 men in 6 days = 12 × 6 = 72 units Best work = 144 – 72 = 72 units Required time for 6 men to complete the work = 72/6 = 12Hence Total time = 12 + 6 = 18 days Extra time = 18 – 12 = 6 days
Related Solutions
A job can be completed by 12 men in 12 days. How many extra days will be needed to complete the job if 6 men leave after working for 6 days?
View SolutionA job can be completed by 12 men in 12 days. How many extra days will be needed to complete the job, if 6 men leave after working for 6 days?
View SolutionA particular job can be completed by a team of 10 men in 12 days. The same job can be completed by a team of 10 women in 6 days. How many days are needed to complete the job if the two teams work together?
View SolutionA can do a job in 12 days and B can do the same job in 6 days, in how many days working together they can complete the job?
View Solutionmen can complete a job in 8 days. How many days will it take if 12 men do the job?
View Solution5 men can complete a job in 8 days. How many days will it take if 12 men do the job?
View Solution24 men can complete a piece of work in 16 days and 18 women can complete the same work in 32 days. 12 men and 6 women work together for 16 days. If the remaining work was to be completed in 2 days, how many additional men would be required besisdes 12 men and 6 women ?
View SolutionFifteen men take 10 days to complete a job working 12 hours a day.How many hours a day should 10 men work to complete the job in 20 days ?
View Solution15 men can complete a work in 24 days and 12 children in 60 days. 10 men started the work and after 12 days 12 children joined the work. In how many days will the remaining work be finished?
View Solution12 आदमी किसी कार्य को 90 दिनों में कर सकते है कार्य छोड़ प्रारभ होने के 30 दिनों के बाद 2 आदमियों ने कार्य को पूरा करने में कितने दिन लगेंगे ?
View Solution12 men can complete a work within 9 days. After 3 days they started the work, 6 men joined them to replace 2 men. How many days will they take to complete the remaining work?
View Solution24 boys can complete a work in 12 days while 16 men can complete the same work in 9 days. In how many days will 12 boys and 12 men together complete the same work ?
View Solution20 men can do a piece of work in 12 days working 9 hours a day. How many men will be required if the same work is to be completed in 24 days working 6 hours a day?
View Solutionयदि 3 पुरुष या 6 महिलाएँ एक काम को 16 दिनों में कर सकती है , तो 12 पुरुष तथा 8 महिलाएँ उसी काम को कितने दिनों में करेंगे ?
View Solution10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days.
View Solution15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
View SolutionIf 10 men can complete a work in 12 days . In how many days can 18 men complete the same work ?
View Solution3 men or 5 women can do a work in 12 days. How long will 6 men and 5 women take to do it? (a) 6 days (b) 5 days (c) 4 days (d) 3 days
View Solution4 पुरुष या 6 लड़के किसी काम को 12 दिनों में पूरा करते हैं, तो 8 पुरुष एवं 6 लड़के उसी काम को उसी गति से कितने दिनों में पूरा करेंगे?
View SolutionX can complete a job in 12 days. If X and Y work together, they can complete the job in 6 days. Y alone can complete the job in
View Solution