24 men can complete a piece of work in 16 days and 18 women can complete the same work in 32 days. 12 men and 6 women work together for 16 days. If the remaining work was to be completed in 2 days, how many additional men would be required besisdes 12 men and 6 women ?
The correct Answer is:16 men
To solve the problem step by step, we will first determine the work done by men and women, then calculate how much work is left after 16 days, and finally find out how many additional men are needed to complete the remaining work in 2 days.
Step 1: Calculate the work done by men and women
1. Work done by 24 men in 16 days:
- Total work = Number of men × Number of days = 24 men × 16 days = 384 man-days.
- Therefore, 1 man can complete 1384 of the work in one day.
2. Work done by 18 women in 32 days:
- Total work = Number of women × Number of days = 18 women × 32 days = 576 woman-days.
- Therefore, 1 woman can complete 1576 of the work in one day.
Step 2: Calculate the work done by 12 men and 6 women in 16 days
1. Work done by 12 men in 1 day:
- Work done by 12 men in 1 day = 12×1384=12384=132.
2. Work done by 6 women in 1 day:
- Work done by 6 women in 1 day = 6×1576=6576=196.
3. Total work done by 12 men and 6 women in 1 day:
- Total work in 1 day = Work done by men + Work done by women = 132+196.
- To add these fractions, we find a common denominator, which is 96:
- 132=396.
- Therefore, 132+196=396+196=496=124.
4. Work done in 16 days:
- Work done in 16 days = 16×124=1624=23.
Step 3: Calculate the remaining work
1. Remaining work:
- Total work = 1 (whole work).
- Work done = 23.
- Remaining work = 1−23=13.
Step 4: Calculate how many additional men are required to complete the remaining work in 2 days
1. Work done by 12 men and 6 women in 2 days:
- Work done by 12 men in 2 days = 2×132=232=116.
- Work done by 6 women in 2 days = 2×196=296=148.
- Total work done in 2 days = 116+148.
- To add these fractions, we find a common denominator, which is 48:
- 116=348.
- Therefore, 116+148=348+148=448=112.
2. Remaining work after 2 days:
- Remaining work = 13−112.
- To subtract these fractions, we find a common denominator, which is 12:
- 13=412.
- Therefore, 13−112=412−112=312=14.
Step 5: Calculate how many additional men are required to complete the remaining work in 2 days
1. Let n be the number of additional men required.
- Work done by 12+n men in 2 days = (12+n)×1384×2.
- This should equal the remaining work 14:
(12+n)×2384=14
- Simplifying gives:
(12+n)×1192=14
- Cross-multiplying:
12+n=48
- Therefore, n=48−12=36.
Final Answer
36 additional men are required.
- Total work = Number of men × Number of days = 24 men × 16 days = 384 man-days.
- Therefore, 1 man can complete 1384 of the work in one day.
- Total work = Number of women × Number of days = 18 women × 32 days = 576 woman-days.
- Therefore, 1 woman can complete 1576 of the work in one day.
- Work done by 12 men in 1 day = 12×1384=12384=132.
- Work done by 6 women in 1 day = 6×1576=6576=196.
- Total work in 1 day = Work done by men + Work done by women = 132+196.
- To add these fractions, we find a common denominator, which is 96:
- 132=396.
- Therefore, 132+196=396+196=496=124.
- Work done in 16 days = 16×124=1624=23.
- Total work = 1 (whole work).
- Work done = 23.
- Remaining work = 1−23=13.
- Work done by 12 men in 2 days = 2×132=232=116.
- Work done by 6 women in 2 days = 2×196=296=148.
- Total work done in 2 days = 116+148.
- To add these fractions, we find a common denominator, which is 48:
- 116=348.
- Therefore, 116+148=348+148=448=112.
- Remaining work = 13−112.
- To subtract these fractions, we find a common denominator, which is 12:
- 13=412.
- Therefore, 13−112=412−112=312=14.
- Work done by 12+n men in 2 days = (12+n)×1384×2.
- This should equal the remaining work 14:
(12+n)×2384=14
- Simplifying gives:
(12+n)×1192=14
- Cross-multiplying:
12+n=48
- Therefore, n=48−12=36.
36 additional men are required.
Topper's Solved these Questions
- TIME AND WORK BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TIME AND WORK EXERCISE - Question Bank - 20 (a)
27 Videos
- TIME AND WORK BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TIME AND WORK EXERCISE - Question Bank - 20 (b)
15 Videos
- SURDS BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - SURDS EXERCISE - UNIT TEST -1
15 Videos
- TRIANGLES BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TRIANGLES EXERCISE - Self Assessment Sheet
10 Videos
Similar Questions
6 men can complete a piece of work in 12 days, 8 women can complete the same piece of work in 18 days and 18 children can do it in 10 days. 4 men, 12 women and 20 children do the work for 2 days. If the remaining work be completed by men only in 1 day, how many men will be required? 36 b. 24 c. 18 d. cannot be determined
View Solution3 men can do a piece of work in 6 days. 5 women can do the same work in 18 days. If 4 men and 10 women work together, then how long will it take to finish the work?
View Solution
Knowledge Check
15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
A40B42C38D3210 men can complete a piece of work in 15 days and 15 women can complete the same work in 12 days. If all the 10 men and 15 women work together, in how many days will the work get completed?
A6B613C623D72312 men can complete a work in 16 days and 16 women can complete the same work in 12 days In how many days will 4 men and 8 women complete that work ?
A16B12C18D10
12 men can complete a piece of work in 16 days. In how many days will 4 men complete the same piece of work?
View Solution2 men can complete a piece of work in 6 days. 2 women can
complete the same piece of work in 9 days. Where as 3
children can complete the same piece of work in 8 days. 3
women and 4 children worked together for 1 day. If only
men were to finish the remaining work in day, how many
total men would be required?
View Solution21 men can complete a piece of work in 427 days. In how many days can 18 men complete the same piece of work?
View Solution24 men can do a work in 16 days while 36 women can do the same work in 24 days. In how many days will 8 men and 6 women together complete the same work ?
View Solution24 boys can complete a work in 12 days while 16 men can complete the same work in 9 days. In how many days will 12 boys and 12 men together complete the same work ?
View Solution