A contract on construction job specifies a penalty for delay of completion beyond acertain date as follows: Rs 200 for Ist day, Rs. 250 for second day, Rs. 300 for thirdday and so on. If the contractor pays Rs 27750 as penalty, find the number of days forwhich the construction work is delayed.
Step by step video & image solution for A contract on construction job specifies a penalty for delay of completion beyond acertain date as follows: Rs 200 for Ist day, Rs. 250 for second day, Rs. 300 for thirdday and so on. If the contractor pays Rs 27750 as penalty, find the number of days forwhich the construction work is delayed. by Maths experts to help you in doubts & scoring excellent marks in Class 12 exams.
Similar Questions
A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day Rs 300 for the third day, etc., the penalty for each succeeding day being Rs 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?
View SolutionA contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day Rs 300 for the third day, etc., the penalty for each succeeding day being Rs 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?
View SolutionA contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day Rs 300 for the third day, etc., the penalty for each succeeding day being Rs 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?
View SolutionA contract on construction job specifies a penalty for delay of completion beyond a certain date as follow : Rs 500 for the first day , Rs 550 for the second day , Rs 600 for the third day , etc the penalty for each suceeding day being Rs 50 more than for the preceding day . How much money the contractor has to pay as penalty , if he has delayed the work by 50 days ?
View SolutionA contract on construction job specifies a penalty for delay of completion beyond a certain days as follows: Rs. 180 for the first day, Rs. 200 for the second day, etc., the penalty for each succeeding day being Rs. 20 more than the preceding day. (i) How much money the contractor has to pay as penalty, if he has delayed the work by 15 days? (ii) For how many days has the contractor delayed the work if he paid Rs. 7400 as penalty?
View SolutionA boy spends Rs. 10 on first day, Rs. 20 on second day, Rs. 40 on third day and so on. Find how much, in all, will he spend in 12 days ?
View SolutionDaya gets pocket money from his father every day. Out of the pocket money, he saves Rs 2.75 on first day, Rs 3.00 on second day, Rs 3.25 on third day and so on. Find:
the total amount saved by him in 30 days.View SolutionDaya gets pocket money from his father every day. Out of the pocket money, he saves Rs 2.75 on first day, Rs 3.00 on second day, Rs 3.25 on third day and so on. Find:
the amount saved by Daya on 30th dayView SolutionDaya gets pocket money from his father every day. Out of the pocket money, he saves Rs 2.75 on first day, Rs 3.00 on second day, Rs 3.25 on third day and so on. Find:
the amount saved by Daya on 14th dayView Solution150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on the third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was complete.
View Solution