Doubtnut Promotions Sticky

A contract on construction job specifies a penalty for delay of completion beyond acertain date as follows: Rs 200 for Ist day, Rs. 250 for second day, Rs. 300 for thirdday and so on. If the contractor pays Rs 27750 as penalty, find the number of days forwhich the construction work is delayed.

Video Solution
Doubtnut Promotions Banner
|
Answer

Step by step video & image solution for A contract on construction job specifies a penalty for delay of completion beyond acertain date as follows: Rs 200 for Ist day, Rs. 250 for second day, Rs. 300 for thirdday and so on. If the contractor pays Rs 27750 as penalty, find the number of days forwhich the construction work is delayed. by Maths experts to help you in doubts & scoring excellent marks in Class 12 exams.

Updated on:21/07/2023

Similar Questions