Doubtnut Promotions Sticky

A contract on construction job specifies a penalty for delay of completion beyond a certain date as follow : Rs 500 for the first day , Rs 550 for the second day , Rs 600 for the third day , etc the penalty for each suceeding day being Rs 50 more than for the preceding day . How much money the contractor has to pay as penalty , if he has delayed the work by 50 days ?

A

Rs 37750

B

Rs 20750

C

Rs 86250

D

Rs 25570

Video Solution
Doubtnut Promotions Banner
|
Answer

Step by step video & image solution for A contract on construction job specifies a penalty for delay of completion beyond a certain date as follow : Rs 500 for the first day , Rs 550 for the second day , Rs 600 for the third day , etc the penalty for each suceeding day being Rs 50 more than for the preceding day . How much money the contractor has to pay as penalty , if he has delayed the work by 50 days ? by Maths experts to help you in doubts & scoring excellent marks in Class 10 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Visitors to a show were charged Rs. 15 each on the first day, Rs. 7.50 on the second day, Rs. 2.50 on the third day and total attendance on three days were in the ratio 2 : 5 : 13 respectively. The average charge per person for the entire three days is

    ARs 5
    BRs 5.50
    CRs 6
    DRs 7
  • Question 2 - Select One

    The school canteen charges Rs 20 for lunch and Rs 4 for milk for each day. How much money do you spend in 5 days on these things?

    A140
    B120
    C105
    D115