A takes 6 days less than the time taken by B to finish a piece of work. If both A and B together can finish it in 4 days . Find the time taken by B to finish the work.
To solve the problem, we need to find the time taken by B to finish the work based on the information given. Let's break it down step by step.
Step 1: Define Variables
Let the time taken by B to finish the work be x days. According to the problem, A takes 6 days less than B. Therefore, the time taken by A to finish the work is:
x−6 days
Step 2: Calculate Work Done Per Day
The work done by A in one day is:
1x−6
The work done by B in one day is:
1x
Step 3: Combined Work Done Per Day
When A and B work together, they can finish the work in 4 days. Therefore, the combined work done by A and B in one day is:
14
Step 4: Set Up the Equation
According to the work done per day, we can set up the equation:
1x−6+1x=14
Step 5: Solve the Equation
To solve this equation, we first find a common denominator, which is x(x−6):
x+(x−6)x(x−6)=14
This simplifies to:
2x−6x(x−6)=14
Now, cross-multiply to eliminate the fractions:
4(2x−6)=x(x−6)
Expanding both sides gives:
8x−24=x2−6x
Step 6: Rearrange the Equation
Rearranging the equation to one side results in:
x2−6x−8x+24=0
This simplifies to:
x2−14x+24=0
Step 7: Factor the Quadratic Equation
Next, we can factor the quadratic equation:
(x−12)(x−2)=0
This gives us two possible solutions:
x=12orx=2
Step 8: Determine Valid Solution
Since A takes x−6 days to finish the work, we check both values:
- If x=12, then A takes 12−6=6 days (valid).
- If x=2, then A takes 2−6=−4 days (not valid).
Thus, the only valid solution is:
x=12
Conclusion
The time taken by B to finish the work is:
12 days
Let the time taken by B to finish the work be x days. According to the problem, A takes 6 days less than B. Therefore, the time taken by A to finish the work is:
x−6 days
The work done by A in one day is:
1x−6
The work done by B in one day is:
1x
When A and B work together, they can finish the work in 4 days. Therefore, the combined work done by A and B in one day is:
14
According to the work done per day, we can set up the equation:
1x−6+1x=14
To solve this equation, we first find a common denominator, which is x(x−6):
x+(x−6)x(x−6)=14
This simplifies to:
2x−6x(x−6)=14
4(2x−6)=x(x−6)
Expanding both sides gives:
8x−24=x2−6x
Rearranging the equation to one side results in:
x2−6x−8x+24=0
This simplifies to:
x2−14x+24=0
Next, we can factor the quadratic equation:
(x−12)(x−2)=0
This gives us two possible solutions:
x=12orx=2
Since A takes x−6 days to finish the work, we check both values:
- If x=12, then A takes 12−6=6 days (valid).
- If x=2, then A takes 2−6=−4 days (not valid).
x=12
The time taken by B to finish the work is:
12 days
Similar Questions
A takes 10 days less than the time taken by B to finish a piece of work. If both A and B together can finish the work in 12 days, find the time taken by B to finish the work.
View SolutionA takes 10 days less than the time taken by B to finish a piece of work. If both A and 6 can do it in 12 days, then the time taken by B alone to finish the work is
View Solution
Knowledge Check
- Question 1 - Select One
X takes 10 days less than the time taken by Y to finish a piece of work, if both X and Y together finish a work in 12 days. Find the time taken by Y to finish the work.
X, किसी कार्य को पूरा करने में Y की तुलना में 10 दिन का कम समय लेता है | X और Y दोनों मिलकर कार्य को 12 दिन में पूरा कर सकते हैं | Y कितने दिनों में अकेले कार्य को पूरा करेगा?A30 daysB27 daysC20 daysD25 days - Question 2 - Select One
When A alone does a piece of work , he takes 25 days more than the time taken (A+B) to completes that particular work, while B alone takes 49 days more than the time taken by (A + B) to finish the same work. A andBtogether will take what time to finish this work?
A35 daysB25 daysC15 daysD45 days
2 men and 5 boys together can finish a piece of work in 4 days, while 3 men and 6 boys can finish it in 3 days. Find the time taken by 1 man alone to finish the work and than taken by 1 boy alone.
View SolutionWhen A alone does a piece of work , he takes 16 days more than the time taken by (A+B) to complete the work, while B alone takes 9 days more than the time taken by (A + B) to finish the work. What time,AandBtogether will take to finish this work?
View Solution4 men and 6 boys can finish a piece of work in 5 days while 3 men and 4 boys can finish it in 7 days , then the time taken by one man alone is
View SolutionA can do a work in 5 days less than the time taken by B to do it. If both of them together take 1119days, then the time taken by B alone to the same work (in days) is
View Solution2 women and 5 men can together finish an embroidery work in 4 days, while 3 women and 6 men can finish it in 3 days. Find the time taken by 1 woman alone to finish the work, and also that taken by 1 man alone.
View SolutionA and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. In how many days can A alone finish the work?
View Solution