A work-force of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must he employ to complete the job in 7 months?
To solve the problem step by step, we will use the concept of direct variation.
Step 1: Understand the given information
We know that 420 men can complete the work in 9 months. We need to find out how many men are required to complete the same work in 7 months.
Step 2: Set up the equation
Let x be the number of men required to complete the work in 7 months. According to the work formula:
Number of men×Time=Constant Work
From the information given:
420 men×9 months=x men×7 months
Step 3: Solve for x
Substituting the values into the equation:
420×9=x×7
Calculating the left side:
3780=x×7
Now, divide both sides by 7 to solve for x:
x=37807=540
Step 4: Calculate the extra men needed
Now, we know that 540 men are required to complete the work in 7 months. Initially, there were 420 men. To find the number of extra men needed, we subtract the initial number of men from the required number:
Extra men=540−420=120
Final Answer
The contractor must employ 120 extra men to complete the job in 7 months.
---
We know that 420 men can complete the work in 9 months. We need to find out how many men are required to complete the same work in 7 months.
Let x be the number of men required to complete the work in 7 months. According to the work formula:
Number of men×Time=Constant Work
From the information given:
420 men×9 months=x men×7 months
Substituting the values into the equation:
420×9=x×7
Calculating the left side:
3780=x×7
Now, divide both sides by 7 to solve for x:
x=37807=540
Now, we know that 540 men are required to complete the work in 7 months. Initially, there were 420 men. To find the number of extra men needed, we subtract the initial number of men from the required number:
Extra men=540−420=120
The contractor must employ 120 extra men to complete the job in 7 months.
Topper's Solved these Questions
Similar Questions
A work force of 50 men with a contractor can finish a piece of work in 5 months. In how many months the same work can be completed by 125 men?
View SolutionAn employer has a workforce of 300 employees to finish a project in 8 months.How many extra employees should he employ to complete the project in 6 months?
View Solution
Knowledge Check
- Question 1 - Select One
If 28 men working 8 hours per day can finish a piece of work in 10 days. How many hours per day 40 men must work to complete the same work in 8 days.
A6 hoursB(6)1/2 hoursC7 hoursD9 hours - Question 2 - Select One
7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?
A28B21C14D7 - Question 3 - Select One
45 men can complete a piece of work in 12 days. In how many days will 36 men be able to complete it?
A10B16C18D15
8 men can finish a piece of work in 15 hours.In how many hours can 20 men finish it?
View SolutionIf 36 men can finish a piece of work in 35 days.how many days will 15 men take to do it ?
View SolutionA contractor undertook a contract to complete a part of a stadium in 9 months with a team of 560 persons. Later on, it was required to complete the job in 5 months. How many extra persons should he employ to complete the work?
View Solution7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work
View Solution15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
View Solution