Doubtnut Promotions Sticky

A work-force of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must he employ to complete the job in 7 months?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will use the concept of direct variation.

Step 1: Understand the given information
We know that 420 men can complete the work in 9 months. We need to find out how many men are required to complete the same work in 7 months.

Step 2: Set up the equation
Let x be the number of men required to complete the work in 7 months. According to the work formula:
Number of men×Time=Constant Work
From the information given:
420 men×9 months=x men×7 months

Step 3: Solve for x
Substituting the values into the equation:
420×9=x×7
Calculating the left side:
3780=x×7
Now, divide both sides by 7 to solve for x:
x=37807=540

Step 4: Calculate the extra men needed
Now, we know that 540 men are required to complete the work in 7 months. Initially, there were 420 men. To find the number of extra men needed, we subtract the initial number of men from the required number:
Extra men=540420=120

Final Answer
The contractor must employ 120 extra men to complete the job in 7 months.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 28 men working 8 hours per day can finish a piece of work in 10 days. How many hours per day 40 men must work to complete the same work in 8 days.

    A6 hours
    B(6)1/2 hours
    C7 hours
    D9 hours
  • Question 2 - Select One

    7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?

    A28
    B21
    C14
    D7
  • Question 3 - Select One

    45 men can complete a piece of work in 12 days. In how many days will 36 men be able to complete it?

    A10
    B16
    C18
    D15