A project manager estimates that a project will take x hours to complete, where x gt 100. The goal is for the estimate to be within 10 hours of the time it will actually take to complete the project. If the manager meets the goal and it takes y hours to complete the project, which of the following inequalities represents the relationship between the estimated time and the actual completion time?
To solve the problem, we need to establish the relationship between the estimated time (x hours) and the actual completion time (y hours) based on the condition that the estimate should be within 10 hours of the actual time.
1. Understanding the Problem:
The project manager estimates that the project will take x hours. The goal is for this estimate to be within 10 hours of the actual time it takes to complete the project, which is y hours.
2. Setting Up the Inequalities:
We need to express the condition that the estimate (x) is within 10 hours of the actual time (y). This can be expressed in two parts:
- The estimated time could be greater than the actual time:
x−y<10
- The estimated time could be less than the actual time:
y−x<10
3. Combining the Inequalities:
The first inequality x−y<10 can be rearranged to:
y>x−10
The second inequality y−x<10 can be rearranged to:
y<x+10
4. Final Inequality:
Combining both inequalities gives us:
x−10<y<x+10
This means that y must be greater than x−10 and less than x+10.
5. Expressing as a Single Inequality:
We can express this relationship as:
−10<y−x<10
This indicates that the difference between the actual time and the estimated time must be within -10 and +10 hours.
Conclusion:
The inequalities that represent the relationship between the estimated time (x) and the actual completion time (y) are:
−10<y−x<10
The project manager estimates that the project will take x hours. The goal is for this estimate to be within 10 hours of the actual time it takes to complete the project, which is y hours.
We need to express the condition that the estimate (x) is within 10 hours of the actual time (y). This can be expressed in two parts:
- The estimated time could be greater than the actual time:
x−y<10
- The estimated time could be less than the actual time:
y−x<10
The first inequality x−y<10 can be rearranged to:
y>x−10
The second inequality y−x<10 can be rearranged to:
y<x+10
Combining both inequalities gives us:
x−10<y<x+10
This means that y must be greater than x−10 and less than x+10.
We can express this relationship as:
−10<y−x<10
This indicates that the difference between the actual time and the estimated time must be within -10 and +10 hours.
The inequalities that represent the relationship between the estimated time (x) and the actual completion time (y) are:
−10<y−x<10
Similar Questions
A man working 8 hours a day takes 5 days to complete a project. How many hours a day must he work to complete. It in 4 days?
01:33View Solutionमनुष्य कोशिका को एक कोशिका चक्र पूरा करने में 24 घंटे लगते हैं। कौन सी प्रावस्था कोशिका चक्र का सबसे अधिक समय लेती है?
02:03View SolutionThe successful completion of all original goals of the human genome project was announced by
02:16View SolutionA man working 8 hours a day takes 5 days to complete a project. How many hours a day must he work to complete it in 4 days ?
02:37View SolutionA takes 6 hours less than B to complete a work. If together they complete the work in 13 hours 20 minutes, find how much time will B alone take to complete the work.
05:38View SolutionA and B can complete a work in 18 hours. After 6 hours A left the work. B takes 36 hours to complete the remaining work. If A works alone, how many hours will he take to complete the work?
03:14View SolutionThe project manager asked Vivek, "How much time will you take to finish this project?"
View SolutionA takes 5 hours more time than that taken by B to complete a work. If working together they can complete a work in 6 hours, then the number of hours that takes to complete the work individually is
03:12View Solution