150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
Let xbe the number of days in which 150 workers finish the work.
According to the given information,
150x=150+146+142+...(x+8)terms
The series 150+146+142+...+(x+8)terms is an A.P. with first term 150, common difference−4 and number of terms as(x+8)
⇒150x=x+82[2(150)+(x+8−1)(−4)]
⇒150x=(x+8)[(150)+(x+7)(−2)]
⇒150x=(x+8)(150−2x−14)
⇒150x=(x+8)(136−2x)
⇒75x=(x+8)(68−x)
⇒75x=68x−x2+544−8x
⇒x2+75x−60x−544=0
⇒x2+15x−544=0
⇒x2+32x−17x−544=0
⇒x+(x+32)−17(x+32)=0
⇒(x−17)(x+32)=0
⇒x=17orx=−32
Since, x cannot be negative .
So, x=17
So, the number of days in which the work was to be completed by 150 workers is 17.
So, required number of days =(17+8)=25
Topper's Solved these Questions
Similar Questions
150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
View SolutionAbout 150 workers were engaged to finish a piece of work in a certain number of days. Four workers stopped working on the second day, four more workers stopped their work on the third day and so on. It took 8 more days to finish the work. Then the number of days in which the work was completed is 29 days b. 24 days c. 25 days d. none of these
View Solution
Knowledge Check
- Question 1 - Select One
150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
A24 daysB40 daysC17 daysD25 days - Question 2 - Select One
56 workers canfinish a piece of work in 14 days. If the work
is to be completed in 8 days, then how many extra workers
are required ?A36B48C44D42 - Question 3 - Select One
8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
A2B3C4D5
150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on the third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was complete.
View SolutionIn a factory, 150 workers were engaged to finish a piece of work in a certain number of days. However, if 4 workers are dropped everyday, except the first day, it will take 8 more days to finish the work. Find the number of days in which the work was to be completed.
View SolutionA is twice as good as B and together they finish a piece of work in 16 days. The number of days taken by A alone to finish the work is
View Solution8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
View SolutionA is thrice as efficient as B. Working together they complete the work in 3 days. If B takes 8 days more than A, what is the number of days taken by A to finish the whole work, alone ?
View Solution