In a factory, 150 workers were engaged to finish a piece of work in a certain number of days. However, if 4 workers are dropped everyday, except the first day, it will take 8 more days to finish the work. Find the number of days in which the work was to be completed.
To solve the problem, we need to find the number of days (N) required to complete the work with 150 workers, considering that 4 workers are dropped every day after the first day, which results in an additional 8 days to complete the work.
1. Define Variables:
Let N be the original number of days required to complete the work with 150 workers.
2. Calculate Total Work:
The total work done can be expressed as:
Total Work=Number of Workers×Number of Days=150×N
3. Work Done with Dropping Workers:
If 4 workers are dropped every day after the first day, the number of workers on each day will be:
- Day 1: 150 workers
- Day 2: 146 workers
- Day 3: 142 workers
- ...
- Day N: 150−4(N−1) workers
The number of workers on the k-th day can be expressed as:
Workers on Day k=150−4(k−1)
4. Total Work with Dropping Workers:
The total work done when dropping 4 workers every day (except the first day) over N+8 days is:
Total Work=150+146+142+…+(150−4(N−1))
This is an arithmetic series where:
- First term a=150
- Last term l=150−4(N−1)=154−4N
- Number of terms =N
The sum of an arithmetic series is given by:
S=n2×(a+l)
Therefore, the total work can be expressed as:
Total Work=N2×(150+(154−4N))=N2×(304−4N)
5. Set Up the Equation:
Since both expressions for total work are equal, we can set them equal to each other:
150N=N2×(304−4N)
6. Simplify the Equation:
Multiply both sides by 2 to eliminate the fraction:
300N=N(304−4N)
Expanding the right side gives:
300N=304N−4N2
Rearranging the equation:
4N2−4N−0=0
Simplifying further:
N2−N−600=0
7. Solve the Quadratic Equation:
Using the quadratic formula N=−b±√b2−4ac2a:
N=−(−1)±√(−1)2−4×1×(−600)2×1
N=1±√1+24002
N=1±√24012
N=1±492
This gives us two possible solutions:
N=502=25orN=−482=−24
Since the number of days cannot be negative, we have:
N=25
8. Conclusion:
The original number of days required to complete the work is 25 days.
Let N be the original number of days required to complete the work with 150 workers.
The total work done can be expressed as:
Total Work=Number of Workers×Number of Days=150×N
If 4 workers are dropped every day after the first day, the number of workers on each day will be:
- Day 1: 150 workers
- Day 2: 146 workers
- Day 3: 142 workers
- ...
- Day N: 150−4(N−1) workers
Workers on Day k=150−4(k−1)
The total work done when dropping 4 workers every day (except the first day) over N+8 days is:
Total Work=150+146+142+…+(150−4(N−1))
This is an arithmetic series where:
- First term a=150
- Last term l=150−4(N−1)=154−4N
- Number of terms =N
S=n2×(a+l)
Therefore, the total work can be expressed as:
Total Work=N2×(150+(154−4N))=N2×(304−4N)
Since both expressions for total work are equal, we can set them equal to each other:
150N=N2×(304−4N)
Multiply both sides by 2 to eliminate the fraction:
300N=N(304−4N)
Expanding the right side gives:
300N=304N−4N2
Rearranging the equation:
4N2−4N−0=0
Simplifying further:
N2−N−600=0
Using the quadratic formula N=−b±√b2−4ac2a:
N=−(−1)±√(−1)2−4×1×(−600)2×1
N=1±√1+24002
N=1±√24012
N=1±492
This gives us two possible solutions:
N=502=25orN=−482=−24
Since the number of days cannot be negative, we have:
N=25
The original number of days required to complete the work is 25 days.
Topper's Solved these Questions
- BOOK - NCERTCHAPTER - SEQUENCES AND SERIESEXERCISE - EXERCISE 9.410videos
SEQUENCES AND SERIES
- BOOK - NCERTCHAPTER - SEQUENCES AND SERIESEXERCISE - EXERCISE 9.218videos
SEQUENCES AND SERIES
- BOOK - NCERTCHAPTER - SEQUENCES AND SERIESEXERCISE - EXERCISE 9.56videos
SEQUENCES AND SERIES
- BOOK - NCERTCHAPTER - RELATIONS AND FUNCTIONSEXERCISE - EXERCISE 2.35videos
RELATIONS AND FUNCTIONS
- BOOK - NCERTCHAPTER - SETSEXERCISE - EXERCISE 1.57videos
SETS
Similar Questions
150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
View Solution150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on the third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was complete.
View Solution
Knowledge Check
- Question 1 - Select One
150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
A24 daysB40 daysC17 daysD25 days - Question 2 - Select One
A contractor planned to finish work in 12 days and employed a certain number of men. However, 6 of them remained absent from the very first day. The rest could finish the work in 20 days. The number of men originally employed were:
एक ठेकेदार ने किसी कार्य को 12 दिनों में समाप्त करने की योजना बनाई और निश्चित संख्या में पुरुषों को काम पर लगाया | हालाँकि, इनमें से 6 पहले ही दिन से अनुपस्थिति रहे | शेष पुरुष इस कार्य को 20 दिनों में समाप्त कर सके |आरंभ में कितने पुरुषों को कार्य पर लगाया गया था ?A24B20C18D15 - Question 3 - Select One
15 men can finish a piece of work in 40 days. The number of days after which 5 men should leave the work so that the work is finished in 45 days altogether is:
A10B20C30D35
About 150 workers were engaged to finish a piece of work in a certain number of days. Four workers stopped working on the second day, four more workers stopped their work on the third day and so on. It took 8 more days to finish the work. Then the number of days in which the work was completed is 29 days b. 24 days c. 25 days d. none of these
View Solution8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
View SolutionIf 8 men can finish a piece of work in 40 days.then 10 men can finish it in 32 days.
View Solution8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
View Solution56 workers canfinish a piece of work in 14 days. If the work
is to be completed in 8 days, then how many extra workers
are required ?View Solution