In a factory, 150 workers were engaged to finish a piece of work in a certain number of days. However, if 4 workers are dropped everyday, except the first day, it will take 8 more days to finish the work. Find the number of days in which the work was to be completed.
series will be like 150+146+142+..........+n
work =n2(2+150+(n−1)(−4))
=(152n−2n2)
if all are working then
w=150(n−8)
152n−2n2=150n−1200
2n2−2n−1200=6
n2−n−600=0
(n−25)(n+24)=0
n=25,−24
as no of days cant be negative so n=25
answer
Topper's Solved these Questions
- BOOK - NCERTCHAPTER - SEQUENCES AND SERIESEXERCISE - EXERCISE 9.410videos
SEQUENCES AND SERIES
- BOOK - NCERTCHAPTER - SEQUENCES AND SERIESEXERCISE - EXERCISE 9.218videos
SEQUENCES AND SERIES
- BOOK - NCERTCHAPTER - SEQUENCES AND SERIESEXERCISE - EXERCISE 9.56videos
SEQUENCES AND SERIES
- BOOK - NCERTCHAPTER - RELATIONS AND FUNCTIONSEXERCISE - EXERCISE 2.35videos
RELATIONS AND FUNCTIONS
- BOOK - NCERTCHAPTER - SETSEXERCISE - EXERCISE 1.57videos
SETS
Similar Questions
150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
View Solution150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on the third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was complete.
View Solution
Knowledge Check
- Question 1 - Select One
150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
A24 daysB40 daysC17 daysD25 days - Question 2 - Select One
A contractor planned to finish work in 12 days and employed a certain number of men. However, 6 of them remained absent from the very first day. The rest could finish the work in 20 days. The number of men originally employed were:
एक ठेकेदार ने किसी कार्य को 12 दिनों में समाप्त करने की योजना बनाई और निश्चित संख्या में पुरुषों को काम पर लगाया | हालाँकि, इनमें से 6 पहले ही दिन से अनुपस्थिति रहे | शेष पुरुष इस कार्य को 20 दिनों में समाप्त कर सके |आरंभ में कितने पुरुषों को कार्य पर लगाया गया था ?A24B20C18D15 - Question 3 - Select One
15 men can finish a piece of work in 40 days. The number of days after which 5 men should leave the work so that the work is finished in 45 days altogether is:
A10B20C30D35
About 150 workers were engaged to finish a piece of work in a certain number of days. Four workers stopped working on the second day, four more workers stopped their work on the third day and so on. It took 8 more days to finish the work. Then the number of days in which the work was completed is 29 days b. 24 days c. 25 days d. none of these
View Solution8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
View SolutionIf 8 men can finish a piece of work in 40 days.then 10 men can finish it in 32 days.
View Solution8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
View Solution56 workers canfinish a piece of work in 14 days. If the work
is to be completed in 8 days, then how many extra workers
are required ?View Solution