10 persons begin to work together on a job but after some days 4 persons leave. As a result the job which could have been completed in 40 days is completed in 50 days. How many days after the commencement of the work did the 4 persons leave?
Step by step video & image solution for 10 persons begin to work together on a job but after some days 4 persons leave. As a result the job which could have been completed in 40 days is completed in 50 days. How many days after the commencement of the work did the 4 persons leave? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Topper's Solved these Questions
Similar Questions
30 persons can finish a job in20 days. After 6 days how many persons should leave the job, so that work is completedina total of 26 days?
View SolutionA man completes a job in 15 days. His son completes the same job in 10 days. If both work together then in how many days the work will be completed ?
View Solution
Knowledge Check
- Question 1 - Select One
25 persons complete a work in 50 days. In how many days will 10 persons complete the work ?
A120B125C100D215 - Question 2 - Select One
A job can be completed by 12 men in 12 days. How many extra days will be needed to complete the job, if 6 men leave after working for 6 days?
A10 daysB12 daysC8 daysD24 days - Question 3 - Select One
A particular job can be completed by a team of 10 men in 12 days. The same job can be completed by a team of 10 women in 6 days. How many days are needed to complete the job if the two teams work together?
A4 daysB6 daysC9 daysD18 days
A job can be completed by 12 men in 12 days. How many extra days will be needed to complete the job if 6 men leave after working for 6 days?
View Solution30 workers can finish a work in 20 days. After how many days should 9 workers leave the job so that the work is completed in total 26 days :
View SolutionTwo persons can complete a piece of work in 9 days. How many more persons are needed to complete double the work in 12 days?
View SolutionTwo persons can complete a piece of work in 9 days. How many more persons are needed to complete double the work in 12 days?
View Solution12 persons can complete half of a work in 9 days. How many persons can complete the same work (whole) in 6 days?
View Solution