A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With the help of C, they did the job in 4 days only. Then, C alone can do the job in 915days b. 925days c. 10 days d. 935days
To solve the problem step by step, we need to determine how long C alone would take to complete the job of laying the railway track.
Step 1: Determine the work done by A and B in one day
- A can complete the work in 16 days, so the work done by A in one day is:
Work by A in one day=116
- B can complete the work in 12 days, so the work done by B in one day is:
Work by B in one day=112
Step 2: Combine the work done by A and B
- The combined work done by A and B in one day is:
Combined work by A and B=116+112
Step 3: Find a common denominator and calculate the combined work
- The least common multiple (LCM) of 16 and 12 is 48. Therefore:
116=348and112=448
- Thus, the combined work is:
348+448=748
Step 4: Calculate the total work done by A, B, and C in one day
- Together, A, B, and C completed the work in 4 days, meaning they did:
Total work done in one day=14
Step 5: Set up the equation for the work done by C
- We know that:
Work by A + Work by B + Work by C=Total work done in one day
Substituting the values we have:
748+Work by C=14
Step 6: Solve for the work done by C
- Convert 14 to a fraction with a denominator of 48:
14=1248
- Now, substituting this into the equation gives:
748+Work by C=1248
- Rearranging gives:
Work by C=1248−748=548
Step 7: Determine how long C takes to complete the work alone
- If C does 548 of the work in one day, then the number of days C takes to complete the entire work is the reciprocal:
Days taken by C=485=9.6 days
- Converting 9.6 days into a mixed fraction gives:
935 days
Final Answer
Thus, C alone can do the job in 935 days.
- A can complete the work in 16 days, so the work done by A in one day is:
Work by A in one day=116
Work by B in one day=112
- The combined work done by A and B in one day is:
Combined work by A and B=116+112
- The least common multiple (LCM) of 16 and 12 is 48. Therefore:
116=348and112=448
- Thus, the combined work is:
348+448=748
- Together, A, B, and C completed the work in 4 days, meaning they did:
Total work done in one day=14
- We know that:
Work by A + Work by B + Work by C=Total work done in one day
Substituting the values we have:
748+Work by C=14
- Convert 14 to a fraction with a denominator of 48:
14=1248
- Now, substituting this into the equation gives:
748+Work by C=1248
- Rearranging gives:
Work by C=1248−748=548
- If C does 548 of the work in one day, then the number of days C takes to complete the entire work is the reciprocal:
Days taken by C=485=9.6 days
- Converting 9.6 days into a mixed fraction gives:
935 days
Thus, C alone can do the job in 935 days.
Topper's Solved these Questions
Similar Questions
A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in 4 days b. 6 days c. 8 days d. 12 days
View SolutionX can complete a job in 12 days. If X and Y work together, they can complete the job in 6(23) days. 'Y' alone can complete the job on
View Solution
Knowledge Check
- Question 1 - Select One
A can do a job in 16 days and B can do the same job in 12 days. With the help of C, they can finish the job in 6 days only. Then, C alone can finish it in
A34 daysB22 daysC36 daysD48 days - Question 2 - Select One
A can paint a house in 45 days and B can do it in 15 days. Along with C, they did the job in 5 days only. Then, C alone can do the job in how many days?
A12B9C15D8 - Question 3 - Select One
A can paint a house in 55 days and B can do it in 66 days. Along with C, they did the job in 12 days only. Then, Calone can do the job In how many days?
A24B44C33D20
X and Y together can finish a job in 6 days. X can alone do the same job in 12 days. How long will Y alone take to do the same job ?
View SolutionA can do a job in 10 days, B can do the same job in 12 days and C can do the same job in 15 days. In how many days they will finish the work together?
View SolutionAmit and Sumit can plough a field in 4 days. Sumit alone can plough the field in 6 days. In how many days will Amit alone plough the field? a. 10 days b. 12 days c. 15 days d. 14 days
View SolutionTanush's firm can lay railway track between two stations in 16 days. Navansh's firm can do the same job in 12 days. With the help of Vridhi's firm, all can lay the track in 4 days. How many days will it take for Vridhi's firm alone to complete the work?
View SolutionA and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is
View Solution