A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in : a. 4 days b. 6 days c. 8 days d. 12 days
To solve the problem, we need to establish the relationships between the times taken by A, B, and C to complete the work and then use this information to find out how long B takes to complete the work alone.
1. Define the Variables:
- Let the time taken by B to complete the work be b days.
- According to the problem, A takes twice as much time as B, so A takes 2b days.
- A also takes thrice as much time as C, so we can express C's time in terms of B's time as well. Since A takes 2b days, we have:
2b=3c⟹c=2b3
2. Calculate the Work Done in One Day:
- The work done by A in one day is 12b.
- The work done by B in one day is 1b.
- The work done by C in one day is 1c=32b.
- Therefore, the total work done by A, B, and C together in one day is:
12b+1b+32b=1+2+32b=62b=3b
3. Set Up the Equation:
- According to the problem, A, B, and C together can finish the work in 2 days. This means that in one day, they complete 12 of the work:
3b=12
4. Solve for b:
- Cross-multiplying gives:
3×2=1×b⟹6=b
- Thus, B can complete the work alone in 6 days.
Conclusion:
B can do the work alone in 6 days.
- Let the time taken by B to complete the work be b days.
- According to the problem, A takes twice as much time as B, so A takes 2b days.
- A also takes thrice as much time as C, so we can express C's time in terms of B's time as well. Since A takes 2b days, we have:
2b=3c⟹c=2b3
- The work done by A in one day is 12b.
- The work done by B in one day is 1b.
- The work done by C in one day is 1c=32b.
- Therefore, the total work done by A, B, and C together in one day is:
12b+1b+32b=1+2+32b=62b=3b
- According to the problem, A, B, and C together can finish the work in 2 days. This means that in one day, they complete 12 of the work:
3b=12
- Cross-multiplying gives:
3×2=1×b⟹6=b
- Thus, B can complete the work alone in 6 days.
B can do the work alone in 6 days.
Topper's Solved these Questions
Similar Questions
A takes twice as much time as B and C take thrice as much time as B to finish a work. Working together, they can finish the work in 12 days. Find the number of days needed for A to do the work alone.
View SolutionA takes 10 days less than the time taken by B to finish a piece of work. If both A and B together can finish the work in 12 days, find the time taken by B to finish the work.
View Solution
Knowledge Check
A takes twice as much time as B and thrice as much time as C finish a piece of work. Working together, they can finish the work in 2 days. A can do the work alone in:
A4 daysB6 daysC8 daysD12 daysA takes thrice as long to do a piece of work as B takes. A and B together can finish a piece of work in 15 days. A alone can do it in-
A30 daysB45 daysC60 daysD120 daysA is twice as good a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work?
A11 daysB21 daysC28 daysD30 days
A takes 6 days less than the time taken by B to finish a piece of work. If both A and B together can finish it in 4 days . Find the time taken by B to finish the work.
View SolutionA can do a piece of work in 15 days, which B can do in 10 days. B worked at it for 8 days. A can finish the remaining work in 2 days b. 3 days c. 5 days d. 10 days
View SolutionA can do in one day three times the work done by B in one day. They together finish 25 of the work in 9 days. The number of days by which B can do the work alone is a. 30 days b. 90 days c. 100 days d. 120 days
View SolutionA can do a piece of work in 20 days and B in 15 days. With help of C, they finish the work in 5 days. C can alone do the work in
View SolutionA can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :
View Solution