Doubtnut Promotions Sticky

A can do a piece of work in 10 days working 8 hours per day. If B is two thirds as efficient as A, then in how many days can B alone do the same piece of work, working 5 hours per day? 15 b. 18 c. 20 d. 24

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we will follow these steps:

Step 1: Calculate the total work done by A
A can complete the work in 10 days, working 8 hours each day. Therefore, the total work done by A can be calculated as:

Total Work=Days×Hours per Day=10×8=80 hours

Step 2: Determine B's efficiency
B is two-thirds as efficient as A. This means that if A can do the work in 80 hours, B will take longer to do the same amount of work. To find out how long B would take to do the same work, we can calculate B's total work time as follows:

Efficiency of B=23×Efficiency of A

Since A takes 80 hours to complete the work, the time taken by B can be calculated as:

Time taken by B=Total WorkEfficiency of B=80 hours23=80×32=120 hours

Step 3: Calculate the number of days B will take working 5 hours per day
Now that we know B takes 120 hours to complete the work, we can find out how many days B will take if he works 5 hours each day:

Days taken by B=Total TimeHours per Day=120 hours5 hours per day=24 days

Final Answer
Thus, B alone can do the same piece of work in 24 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a piece of work in 24 days. If B is 50% more efficient than A, then in how many days can B do the same work?

    A12
    B16
    C18
    D15
  • Question 2 - Select One

    A can do a piece of work in 48 days. If B is 50% more efficient than A, then in how many days can B do the same work?

    A24
    B32
    C18
    D15
  • Question 3 - Select One

    A alone can do a work in 15 days. A is 20% less efficient than B. In how many days can B alone do the work?

    Aa. 12
    Bb. 18
    Cc. 20
    Dd. 24