Doubtnut Promotions Sticky

A can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone?

A

10 days

B

9 days

C

12 days

D

15 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we need to find out how many days C can complete the work alone after A and B have worked together for 5 days.

Step 1: Calculate the work done by A and B in one day.

- A can complete the work in 12 days, so A's work rate is 112 of the work per day.
- B can complete the work in 20 days, so B's work rate is 120 of the work per day.

Hint: To find the work done in one day, use the formula: Work rate = Total work / Time taken.

Step 2: Find the combined work rate of A and B.

To find the combined work rate of A and B, we add their individual work rates:

Combined work rate=112+120

To add these fractions, we need a common denominator. The least common multiple of 12 and 20 is 60.

112=560,120=360

So,

Combined work rate=560+360=860=215

Hint: When adding fractions, find a common denominator to make the addition easier.

Step 3: Calculate the total work done by A and B in 5 days.

Now, we can find out how much work A and B can complete together in 5 days:

Work done in 5 days=5×215=1015=23

Hint: To find the total work done over multiple days, multiply the daily work rate by the number of days.

Step 4: Determine the remaining work.

Since A and B completed 23 of the work, the remaining work is:

Remaining work=123=13

Hint: To find the remaining work, subtract the completed work from the total work (which is considered as 1).

Step 5: Calculate C's work rate.

C completes the remaining work in 3 days, so C's work rate is:

C's work rate=13 (work)÷3 (days)=19

Hint: To find the work rate, divide the amount of work by the time taken.

Step 6: Find out how many days C can do the work alone.

To find out how many days C can complete the entire work alone, we take the reciprocal of C's work rate:

Days taken by C=119=9 days

Hint: To find the time taken to complete the work, take the reciprocal of the work rate.

Final Answer:

C can complete the same work alone in 9 days.

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?

    A12 days
    B15 days
    C10 days
    D8 days
  • Question 2 - Select One

    A can complete one-third of a work in 10 days and B can do 35th of the same work in 24 days. They worked together for 10 days. The remaining work was completed by C alone in 15 days. In how many days can C alone do 23 of the same work?

    ARs. 12,800
    BRs. 12,500
    CRs. 13,200
    DRs. 12,000
  • Question 3 - Select One

    A can do a work in 10 days and B can do the same in 20 days. If they start the work together and A leaves that work 5 days before completion, in how many days the work will be finished?

    A10
    B8
    C12
    D9