A can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone?
10 days
9 days
12 days
15 days
The correct Answer is:B
To solve the problem step by step, we need to find out how many days C can complete the work alone after A and B have worked together for 5 days.
Step 1: Calculate the work done by A and B in one day.
- A can complete the work in 12 days, so A's work rate is 112 of the work per day.
- B can complete the work in 20 days, so B's work rate is 120 of the work per day.
Hint: To find the work done in one day, use the formula: Work rate = Total work / Time taken.
Step 2: Find the combined work rate of A and B.
To find the combined work rate of A and B, we add their individual work rates:
Combined work rate=112+120
To add these fractions, we need a common denominator. The least common multiple of 12 and 20 is 60.
112=560,120=360
So,
Combined work rate=560+360=860=215
Hint: When adding fractions, find a common denominator to make the addition easier.
Step 3: Calculate the total work done by A and B in 5 days.
Now, we can find out how much work A and B can complete together in 5 days:
Work done in 5 days=5×215=1015=23
Hint: To find the total work done over multiple days, multiply the daily work rate by the number of days.
Step 4: Determine the remaining work.
Since A and B completed 23 of the work, the remaining work is:
Remaining work=1−23=13
Hint: To find the remaining work, subtract the completed work from the total work (which is considered as 1).
Step 5: Calculate C's work rate.
C completes the remaining work in 3 days, so C's work rate is:
C's work rate=13 (work)÷3 (days)=19
Hint: To find the work rate, divide the amount of work by the time taken.
Step 6: Find out how many days C can do the work alone.
To find out how many days C can complete the entire work alone, we take the reciprocal of C's work rate:
Days taken by C=119=9 days
Hint: To find the time taken to complete the work, take the reciprocal of the work rate.
Final Answer:
C can complete the same work alone in 9 days.
- B can complete the work in 20 days, so B's work rate is 120 of the work per day.
Similar Questions
A and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days. A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?
View SolutionA can do a piece of work in 20 days and B in 15 days. With help of C, they finish the work in 5 days. C can alone do the work in
View Solution
Knowledge Check
- Question 1 - Select One
A can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?
A12 daysB15 daysC10 daysD8 days - Question 2 - Select One
A can complete one-third of a work in 10 days and B can do 35th of the same work in 24 days. They worked together for 10 days. The remaining work was completed by C alone in 15 days. In how many days can C alone do 23 of the same work?
ARs. 12,800BRs. 12,500CRs. 13,200DRs. 12,000 - Question 3 - Select One
A can do a work in 10 days and B can do the same in 20 days. If they start the work together and A leaves that work 5 days before completion, in how many days the work will be finished?
A10B8C12D9
A and B can finish a work together in 12 days, and B and C together in 16 days. If A alone works for 5 days and then B alone continues for 7 days, then remaining work is done by C in 13 days. In how many days can C alone finish the complete work?
View Solution(A + B) can do a piece of work in 12 days. (B + C) can do same work in 16 days. A work for 5 days, B works for 7 days and C completed the remaining work in 13 days. In how many days will A, B and C do this work alone ?
View SolutionA can do a piece of work in 120 days and B can do it in 150 days. The work together for 20 days. Then, B leave and A alone continues the work. 12 days after that C joins A and the work is completed in 48 days more. In how many days can C do it, if he works alone?
View SolutionA can do a piece of work in 120 days and B can do it in 150 days. They work together for 20 days. Then B leaves and A alone continues the work. 12 days after that C joins A and the work is completed in 48 days more. In how many days can C do it if he works alone?
View SolutionA' can do a piece of work in 4 days and B in 12 days. In how many days can A and B together complete the same piece of work ?
View Solution