Doubtnut Promotions Sticky

6 men can complete a piece of work in 12 days, 8 women can complete the same piece of work in 18 days and 18 children can do it in 10 days. 4 men, 12 women and 20 children do the work for 2 days. If the remaining work be completed by men only in 1 day, how many men will be required? 36 b. 24 c. 18 d. cannot be determined

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will first determine the work done by each group (men, women, and children) in one day, then calculate the work done by 4 men, 12 women, and 20 children in 2 days, and finally find out how many men are needed to complete the remaining work in 1 day.

Step 1: Calculate the work done by 1 man in 1 day
Given that 6 men can complete the work in 12 days, the total work can be represented in terms of man-days:
Total work=6 men×12 days=72 man-days
Thus, the work done by 1 man in 1 day is:
Work done by 1 man in 1 day=172 of the work

Step 2: Calculate the work done by 1 woman in 1 day
Given that 8 women can complete the work in 18 days:
Total work=8 women×18 days=144 woman-days
Thus, the work done by 1 woman in 1 day is:
Work done by 1 woman in 1 day=1144 of the work

Step 3: Calculate the work done by 1 child in 1 day
Given that 18 children can complete the work in 10 days:
Total work=18 children×10 days=180 child-days
Thus, the work done by 1 child in 1 day is:
Work done by 1 child in 1 day=1180 of the work

Step 4: Calculate the total work done by 4 men, 12 women, and 20 children in 1 day
Now we can calculate the total work done in one day by 4 men, 12 women, and 20 children:
Work done by 4 men in 1 day=4×172=472=118
Work done by 12 women in 1 day=12×1144=12144=112
Work done by 20 children in 1 day=20×1180=20180=19

Now, we add these contributions together:
Total work done in 1 day=118+112+19
To add these fractions, we find a common denominator, which is 36:
118=236,112=336,19=436
Thus,
Total work done in 1 day=236+336+436=936=14

Step 5: Calculate the work done in 2 days
In 2 days, the total work done is:
Total work done in 2 days=2×14=12

Step 6: Calculate the remaining work
Since the total work is 1, the remaining work after 2 days is:
Remaining work=112=12

Step 7: Calculate how many men are needed to complete the remaining work in 1 day
We know that 1 man can do 172 of the work in 1 day. To find out how many men are needed to complete 12 of the work in 1 day, we set up the equation:
x×172=12
Solving for x:
x=1/21/72=12×72=36

Conclusion
Thus, the number of men required to complete the remaining work in 1 day is 36.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?

    A40
    B42
    C38
    D32
  • Question 2 - Select One

    12 men can complete a piece of work in 16 days. In how many days will 4 men complete the same piece of work?

    A60 days
    B45 days
    C54 days
    D48 days
  • Question 3 - Select One

    21 men can complete a piece of work in 427 days. In how many days can 18 men complete the same piece of work?

    A6days
    B5days
    C4days
    D7days