16 men can finish a work in 24 days and 48 boys can finish the same work in 16 days. 12 men started the work and after 4 days 12 boys joined them. In how many days can they finish the remaining work? 6 b. 12 c. 16 d. none of these
To solve the problem step by step, we will first determine the work done by men and boys, and then calculate how much work remains after the initial days of work.
Step 1: Calculate the work done by one man in one day
Given that 16 men can finish the work in 24 days, we can find the work done by one man in one day.
Total work=16 men×24 days=384 man-days
So, the work done by one man in one day is:
Work done by 1 man in 1 day=1384 of the work
Step 2: Calculate the work done by one boy in one day
Given that 48 boys can finish the same work in 16 days, we can find the work done by one boy in one day.
Total work=48 boys×16 days=768 boy-days
So, the work done by one boy in one day is:
Work done by 1 boy in 1 day=1768 of the work
Step 3: Calculate the work done by 12 men in 4 days
Now, we find out how much work 12 men can do in 4 days.
Work done by 12 men in 1 day=12×1384=12384=132
So, in 4 days, the work done by 12 men is:
Work done in 4 days=4×132=432=18
Step 4: Calculate the remaining work
The total work is considered as 1 (whole work). After 4 days, the remaining work is:
Remaining work=1−18=78
Step 5: Calculate the combined work done by 12 men and 12 boys in one day
Now, after 4 days, 12 boys join the 12 men. We need to calculate how much work they can do together in one day.
Work done by 12 boys in 1 day=12×1768=12768=164
Thus, the total work done by 12 men and 12 boys in one day is:
Total work done in 1 day=132+164
To add these fractions, we find a common denominator (which is 64):
132=264
So,
Total work done in 1 day=264+164=364
Step 6: Calculate the number of days to finish the remaining work
Now we need to find out how many days it will take to finish the remaining 78 of the work:
Days required=Remaining workWork done in 1 day=78364=78×643=7×648×3=44824=563
Step 7: Convert to mixed number
563 can be converted to a mixed number:
563=1823 days
Conclusion
Thus, the total time taken to finish the remaining work is 1823 days, which is not listed in the options provided.
Final Answer
The correct option is d. none of these.
---
Given that 16 men can finish the work in 24 days, we can find the work done by one man in one day.
Given that 48 boys can finish the same work in 16 days, we can find the work done by one boy in one day.
Now, we find out how much work 12 men can do in 4 days.
The total work is considered as 1 (whole work). After 4 days, the remaining work is:
Now, after 4 days, 12 boys join the 12 men. We need to calculate how much work they can do together in one day.
Now we need to find out how many days it will take to finish the remaining 78 of the work:
563 can be converted to a mixed number:
Thus, the total time taken to finish the remaining work is 1823 days, which is not listed in the options provided.
The correct option is d. none of these.
Topper's Solved these Questions
Similar Questions
Knowledge Check
A can finish work in 20 days and B can finish the same work in 25 days. They began together, but B left the work after 5 days. How many more days will A take to finish the remaining work?
A 20 दिनों में कार्य समाप्त कर सकता है तथा B इसी कार्य को 25 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य करना शुरू किया, लेकिन B ने 5 दिनों के बाद कार्य छोड़ दिया | शेष कार्य पूरा करने में A को कितने अतिरिक्त दिन लगेंगे ?A16B8C21D11A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
A5B512C6D8A can finish a work in 18 days and B can do the same work in 15 days B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
(A) 5
(B) 5
(D) 8
(C) 6A8B5C4D6
If 12 men and 16 boys can finish a work in 5 days, while 13 men and 24 boys can finish the same work in 4 days. Compare the one day work of 1 man and 1 boy.
View SolutionA can finish a work in 7 days. B can finish the same work in 9 days. The days required to finish the work by both of them together.
View SolutionIf 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same piece of work?
View SolutionA can do a work in 12 days and B can do it in 16 days. A and B started the work jointly and A left 2 days before the work is finished. Find the number of days they took to finish the work.
View SolutionIf 14 men and 12 boys can finish work in 4 days , while 8 men and 16 boys can finish the same work in 5 days . Compare the 1 day work of 1 man and 1 boy .
View Solution