16 men can finish a work in 24 days and 48 boys can finish the same work in 16 days. 12 men started the work and after 4 days 12 boys joined them. In how many days can they finish the remaining work? 6 b. 12 c. 16 d. none of these

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will first determine the work done by men and boys, and then calculate how much work remains after the initial days of work.

Step 1: Calculate the work done by one man in one day
Given that 16 men can finish the work in 24 days, we can find the work done by one man in one day.

Total work=16 men×24 days=384 man-days

So, the work done by one man in one day is:

Work done by 1 man in 1 day=1384 of the work

Step 2: Calculate the work done by one boy in one day
Given that 48 boys can finish the same work in 16 days, we can find the work done by one boy in one day.

Total work=48 boys×16 days=768 boy-days

So, the work done by one boy in one day is:

Work done by 1 boy in 1 day=1768 of the work

Step 3: Calculate the work done by 12 men in 4 days
Now, we find out how much work 12 men can do in 4 days.

Work done by 12 men in 1 day=12×1384=12384=132

So, in 4 days, the work done by 12 men is:

Work done in 4 days=4×132=432=18

Step 4: Calculate the remaining work
The total work is considered as 1 (whole work). After 4 days, the remaining work is:

Remaining work=118=78

Step 5: Calculate the combined work done by 12 men and 12 boys in one day
Now, after 4 days, 12 boys join the 12 men. We need to calculate how much work they can do together in one day.

Work done by 12 boys in 1 day=12×1768=12768=164

Thus, the total work done by 12 men and 12 boys in one day is:

Total work done in 1 day=132+164

To add these fractions, we find a common denominator (which is 64):

132=264

So,

Total work done in 1 day=264+164=364

Step 6: Calculate the number of days to finish the remaining work
Now we need to find out how many days it will take to finish the remaining 78 of the work:

Days required=Remaining workWork done in 1 day=78364=78×643=7×648×3=44824=563

Step 7: Convert to mixed number
563 can be converted to a mixed number:

563=1823 days

Conclusion
Thus, the total time taken to finish the remaining work is 1823 days, which is not listed in the options provided.

Final Answer
The correct option is d. none of these.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can finish work in 20 days and B can finish the same work in 25 days. They began together, but B left the work after 5 days. How many more days will A take to finish the remaining work?
    A 20 दिनों में कार्य समाप्त कर सकता है तथा B इसी कार्य को 25 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य करना शुरू किया, लेकिन B ने 5 दिनों के बाद कार्य छोड़ दिया | शेष कार्य पूरा करने में A को कितने अतिरिक्त दिन लगेंगे ?

    A16
    B8
    C21
    D11
  • A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?

    A5
    B512
    C6
    D8
  • A can finish a work in 18 days and B can do the same work in 15 days B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
    (A) 5
    (B) 5
    (D) 8
    (C) 6

    A8
    B5
    C4
    D6