Theere are 4 people whow can complete a work in 19 days. Individually. The work is started by one of people on the first day. Everyday one more person joins and starting from the 4th days, all of the 4 people work be completed?
614 days
6119days
7 days
7119 days
The correct Answer is:A
To solve the problem step by step, we will follow the process of calculating the work done by each person and the total work completed over the days.
1. Understanding the Work Rate:
Each of the 4 people can complete the work in 19 days. Therefore, the work done by one person in one day is:
Work done by one person in one day=119
2. Calculating Work Done Each Day:
- Day 1: Only 1 person works:
Work done on Day 1=119
- Day 2: 1 more person joins, so 2 people work:
Work done on Day 2=2×119=219
- Day 3: 1 more person joins, so 3 people work:
Work done on Day 3=3×119=319
- Day 4: All 4 people work:
Work done on Day 4=4×119=419
3. Calculating Total Work Done in 4 Days:
Now, we add the work done over the first 4 days:
Total work done in 4 days=119+219+319+419=1019
4. Calculating Remaining Work:
The total work is considered as 1 (the whole work). Therefore, the remaining work after 4 days is:
Remaining work=1−1019=19−1019=919
5. Calculating Work Done by 4 People Together:
From Day 5 onwards, all 4 people work together. The work done by 4 people in one day is:
Work done by 4 people in one day=4×119=419
6. Calculating Days Required to Complete Remaining Work:
To find out how many days (let's call it X) are needed to complete the remaining work of 919:
419×X=919
Solving for X:
X=919÷419=94=2.25 days
7. Total Days Taken:
The total number of days taken to complete the work is:
Total days=4 (initial days)+2.25 (additional days)=6.25 days
Final Answer:
The total time taken to complete the work is 6.25 days.
Each of the 4 people can complete the work in 19 days. Therefore, the work done by one person in one day is:
Work done by one person in one day=119
- Day 1: Only 1 person works:
Work done on Day 1=119
- Day 2: 1 more person joins, so 2 people work:
Work done on Day 2=2×119=219
- Day 3: 1 more person joins, so 3 people work:
Work done on Day 3=3×119=319
- Day 4: All 4 people work:
Work done on Day 4=4×119=419
Now, we add the work done over the first 4 days:
Total work done in 4 days=119+219+319+419=1019
The total work is considered as 1 (the whole work). Therefore, the remaining work after 4 days is:
Remaining work=1−1019=19−1019=919
From Day 5 onwards, all 4 people work together. The work done by 4 people in one day is:
Work done by 4 people in one day=4×119=419
To find out how many days (let's call it X) are needed to complete the remaining work of 919:
419×X=919
Solving for X:
X=919÷419=94=2.25 days
The total number of days taken to complete the work is:
Total days=4 (initial days)+2.25 (additional days)=6.25 days
The total time taken to complete the work is 6.25 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
A group of workers can complete a piece of work in 50 days, when they are working individually. On the first day one person works, on the second day another person joins him, on the third day one more person joins them and this process continues till the work is completed. How many approximate days are needed to complete the work?
A8 daysB9 daysC10 daysD11 daysA, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?
A9 daysB15 daysC12 daysD14 days14 persons can complete a work in 16 days. 8 persons started the work 12 days after they started the work 8 more persons joined them. How many days will they take to complete the remaining work ?
A12 daysB7 daysC9 daysDNone of these
40 people can complete a work in 40 days. They started the work together but 5 people had to leave the work on every tenth day. In how much time the work would be completed?
View SolutionTheere are 5 men in group. Each man can complete a job in 35 days. One of them starts it . Starting from the second day, a man joins until the 5th day. Therefore, all the men work together. Find the total time taken to complete the job. ( in days)
View Solution25 persons can complete a work in 60 days. They started the work. 10 people left the work after x days. If the whole work was completed in 80 days, then what is the value of x ?
25 व्यक्ति किसी कार्य को 60 दिनों में पूरा कर सकते हैं | उन्होंने कार्य शुरू किया | x दिनों के बाद 10 लोगों ने कार्य छोड़ दिया | यदि पूरा कार्य 80 दिनों में पूरा हुआ, तो x का मान ज्ञात करें |
View Solution50 people can complete a work in 50 days. They started the work together but at the end of every 10th day 5 people join the work. In how much time the work would be completed?
View Solution14 men can complete a work in 12 days. 4 days after they started the work, 2 more men joined them. How many days will they take to complete the remaining work ?
View Solution