Doubtnut Promotions Sticky

Theere are 4 people whow can complete a work in 19 days. Individually. The work is started by one of people on the first day. Everyday one more person joins and starting from the 4th days, all of the 4 people work be completed?

A

614 days

B

6119days

C

7 days

D

7119 days

Video Solution
Text Solution
Verified by Experts

The correct Answer is:A


(i) Work done in the first three dya is 119+219+319 and find the 4th day onwards the work done is 419
(ii) Part of the work done in first three days 119+219+319=619
Remaining work =1319
(iii) Let required time =(3+x) days.

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A group of workers can complete a piece of work in 50 days, when they are working individually. On the first day one person works, on the second day another person joins him, on the third day one more person joins them and this process continues till the work is completed. How many approximate days are needed to complete the work?

    A8 days
    B9 days
    C10 days
    D11 days
  • Question 2 - Select One

    A, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?

    A9 days
    B15 days
    C12 days
    D14 days
  • Question 3 - Select One

    14 persons can complete a work in 16 days. 8 persons started the work 12 days after they started the work 8 more persons joined them. How many days will they take to complete the remaining work ?

    A12 days
    B7 days
    C9 days
    DNone of these