Theere are 4 people whow can complete a work in 19 days. Individually. The work is started by one of people on the first day. Everyday one more person joins and starting from the 4th days, all of the 4 people work be completed?

A

614 days

B

6119days

C

7 days

D

7119 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will follow the process of calculating the work done by each person and the total work completed over the days.

1. Understanding the Work Rate:
Each of the 4 people can complete the work in 19 days. Therefore, the work done by one person in one day is:
Work done by one person in one day=119

2. Calculating Work Done Each Day:
- Day 1: Only 1 person works:
Work done on Day 1=119
- Day 2: 1 more person joins, so 2 people work:
Work done on Day 2=2×119=219
- Day 3: 1 more person joins, so 3 people work:
Work done on Day 3=3×119=319
- Day 4: All 4 people work:
Work done on Day 4=4×119=419

3. Calculating Total Work Done in 4 Days:
Now, we add the work done over the first 4 days:
Total work done in 4 days=119+219+319+419=1019

4. Calculating Remaining Work:
The total work is considered as 1 (the whole work). Therefore, the remaining work after 4 days is:
Remaining work=11019=191019=919

5. Calculating Work Done by 4 People Together:
From Day 5 onwards, all 4 people work together. The work done by 4 people in one day is:
Work done by 4 people in one day=4×119=419

6. Calculating Days Required to Complete Remaining Work:
To find out how many days (let's call it X) are needed to complete the remaining work of 919:
419×X=919
Solving for X:
X=919÷419=94=2.25 days

7. Total Days Taken:
The total number of days taken to complete the work is:
Total days=4 (initial days)+2.25 (additional days)=6.25 days

Final Answer:
The total time taken to complete the work is 6.25 days.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A group of workers can complete a piece of work in 50 days, when they are working individually. On the first day one person works, on the second day another person joins him, on the third day one more person joins them and this process continues till the work is completed. How many approximate days are needed to complete the work?

    A8 days
    B9 days
    C10 days
    D11 days
  • A, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?

    A9 days
    B15 days
    C12 days
    D14 days
  • 14 persons can complete a work in 16 days. 8 persons started the work 12 days after they started the work 8 more persons joined them. How many days will they take to complete the remaining work ?

    A12 days
    B7 days
    C9 days
    DNone of these