Doubtnut Promotions Sticky

A' can finish certain work in one day and B can finish the same work in two days. The ratio of energy spent by A to that spent by B is ______.

Text Solution
Verified by Experts

The correct Answer is:1:1

Doubtnut Promotions Banner
|
Updated on:21/07/2023

Related Playlists


Knowledge Check

  • Question 1 - Select One

    A can finish a work in 7 days. B can finish the same work in 9 days. The days required to finish the work by both of them together.

    A11516
    B21516
    C31516
    D41516
  • Question 1 - Select One

    A can finish work in 20 days and B can finish the same work in 25 days. They began together, but B left the work after 5 days. How many more days will A take to finish the remaining work?
    A 20 दिनों में कार्य समाप्त कर सकता है तथा B इसी कार्य को 25 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य करना शुरू किया, लेकिन B ने 5 दिनों के बाद कार्य छोड़ दिया | शेष कार्य पूरा करने में A को कितने अतिरिक्त दिन लगेंगे ?

    A16
    B8
    C21
    D11
  • Question 1 - Select One

    A can finish a work in 15 days and B can do the same work in twice the time taken by A. then, working together, what part of the same work they can finish in five days?

    A12
    B45
    C13
    D15
  • Question 1 - Select One

    A can finish a work in 15 days and B can do the same work in twice the time taken by A. then, working together. What part of the same work they can finish in five days ?

    A12
    B45
    C13
    D15
  • Question 1 - Select One

    A can finish a work in 18 days and B can do the same work in 15 days B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
    (A) 5
    (B) 5
    (D) 8
    (C) 6

    A8
    B5
    C4
    D6
  • Question 1 - Select One

    A can complete a work in 18 days, B can do the same work in half the time as A. What part of work can be completed by both of them working together in 1 day

    A16
    B25
    C19
    D27
  • Question 1 - Select One

    A can complete a piece of work in 18 days and B can complete the same work in half time taken by A. Then, working together, what part of the same work they can complete in a day?

    A16
    B25
    C19
    D27
  • Question 1 - Select One

    A can finish a task in 45 days and B can finish the same task in 30 days. They work together for 3 days and then A leaves. In how many days will B finish the remaining task?

    A5
    B18
    C25
    D20

Similar Questions