A' can finish certain work in one day and B can finish the same work in two days. The ratio of energy spent by A to that spent by B is ______.
The correct Answer is:1:1
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - DYNAMICSEXERCISE - Level 221videos
DYNAMICS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - DYNAMICSEXERCISE - Level 314videos
DYNAMICS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - DYNAMICSEXERCISE - Essay Type Questions5videos
DYNAMICS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - CHEMICAL EFFECTS OF ELECTRIC CURRENTEXERCISE - COMPETITION CORNER (MCQ)48videos
CHEMICAL EFFECTS OF ELECTRIC CURRENT
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - ELECTRICITYEXERCISE - CONCEPT APPLICATION (Level 3)10videos
ELECTRICITY
Similar Questions
16 men can finish a work in 24 days and 48 boys can finish the same work in 16 days. 12 men started the work and after 4 days 12 boys joined them. In how many days can they finish the remaining work? 6 b. 12 c. 16 d. none of these
View SolutionIf 12 men and 16 boys can finish a work in 5 days, while 13 men and 24 boys can finish the same work in 4 days. Compare the one day work of 1 man and 1 boy.
View Solution
Knowledge Check
- Question 1 - Select One
A can finish a work in 7 days. B can finish the same work in 9 days. The days required to finish the work by both of them together.
A11516B21516C31516D41516 - Question 2 - Select One
A can finish work in 20 days and B can finish the same work in 25 days. They began together, but B left the work after 5 days. How many more days will A take to finish the remaining work?
A 20 दिनों में कार्य समाप्त कर सकता है तथा B इसी कार्य को 25 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य करना शुरू किया, लेकिन B ने 5 दिनों के बाद कार्य छोड़ दिया | शेष कार्य पूरा करने में A को कितने अतिरिक्त दिन लगेंगे ?A16B8C21D11 - Question 3 - Select One
A can finish a work in 15 days and B can do the same work in twice the time taken by A. then, working together, what part of the same work they can finish in five days?
A12B45C13D15
A can finish a work in 15 days and B can do the same work in twice the time taken by A. then, working together. What part of the same work they can finish in five days ?
View SolutionA can finish a work in 18 days and B can do the same work in 15 days B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
(A) 5
(B) 5
(D) 8
(C) 6View SolutionA can complete a work in 18 days, B can do the same work in half the time as A. What part of work can be completed by both of them working together in 1 day
View SolutionA can complete a piece of work in 18 days and B can complete the same work in half time taken by A. Then, working together, what part of the same work they can complete in a day?
View SolutionA can finish a task in 45 days and B can finish the same task in 30 days. They work together for 3 days and then A leaves. In how many days will B finish the remaining task?
View Solution