Doubtnut Promotions Sticky

A' can finish certain work in one day and B can finish the same work in two days. The ratio of energy spent by A to that spent by B is ______.

Text Solution
Verified by Experts

The correct Answer is:1:1

Doubtnut Promotions Banner
|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can finish a work in 7 days. B can finish the same work in 9 days. The days required to finish the work by both of them together.

    A11516
    B21516
    C31516
    D41516
  • Question 2 - Select One

    A can finish work in 20 days and B can finish the same work in 25 days. They began together, but B left the work after 5 days. How many more days will A take to finish the remaining work?
    A 20 दिनों में कार्य समाप्त कर सकता है तथा B इसी कार्य को 25 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य करना शुरू किया, लेकिन B ने 5 दिनों के बाद कार्य छोड़ दिया | शेष कार्य पूरा करने में A को कितने अतिरिक्त दिन लगेंगे ?

    A16
    B8
    C21
    D11
  • Question 3 - Select One

    A can finish a work in 15 days and B can do the same work in twice the time taken by A. then, working together, what part of the same work they can finish in five days?

    A12
    B45
    C13
    D15