Fifteen men take 10 days to complete a job working 12 hours a day.How many hours a day should 10 men work to complete the job in 20 days ?
Since 15 men take 10 days working 12 hours per day, the total work done measured in terms of man-hours is 15×1012.
When 10 men are required to complete the same job in 20 days working h hours a day, work done =10×20×h. But 10×20×h=15×10×12. Hence the number of hours for which they should work per day is 15×10×1210×20=9.
∴ 10 men can complete the work in 20 days working for 9 hours per day.
Hence, in general we can say that:
If M1 men can do W1 units of work in D1 days working H1 hours per day and M2 men can do
W2 untis of work in D2 days working H2 hours per day, then M1D1H1W1=M2D2H2W2
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - TEST YOUR CONCEPTS (Very Short Answer Type Questions)30videos
TIME AND WORK, PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - Short Answer Type Questions15videos
TIME AND WORK, PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)7videos
TIME AND WORK PIPES AND CISTERNS
Similar Questions
Fifteen men take 10 days to complete a job working 12 hours a day.How many hours a day should 10 men work to complete the job in 20 days ?
View SolutionFifteen men take 10 days to complete a job working 12hours a day. How many hours in a day should 10 men work to complete the same job in 20 days?
View Solution
Knowledge Check
- Question 1 - Select One
15 men take 20 days to com plete a job working 8 hours a day. The number of hours a day should 20 men take to complete the job in 12 days
A5 hoursB10 hoursC15 hoursD18 hours - Question 2 - Select One
Fifteen men take 30 days to complete a piece of work, working 8 hours a day. Find the time taken by 30 men to complete 5 times as much work, working 10 hours a day.
A30 daysB45 daysC60 daysD15 days - Question 3 - Select One
Fifteen men take 30 days to complete a piece of work, working 8 hours a day. Find the time taken by 30 men to complete 5 times as much work, working 10 hours a day.
A30 daysB45 daysC60 daysD15 days
10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days.
View Solution10 men, working. 6 hours a day can compJete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days?
View SolutionA man working 8 hours a day takes 5 days to complete a project. How many hours a day must he work to complete. It in 4 days?
View SolutionIf 16 men working 12 hours a day can complete a work in 27 days, then working for how many hours a day can 18 men complete the work in 24 days ?
यदि 16 पुरुष प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 27 दिनों में पूरा करते हैं, तो इस कार्य को 24 दिनों में पूरा करने के लिए 18 पुरुषों को दिन में कितने घंटे कार्य करना पड़ेगा ?View SolutionIf 20 men complete a work in 56 days by working 10 hours a day how many days will 40 men take to complete the same work by working 8 hours a day?
View Solution