Doubtnut Promotions Sticky

Fifteen men take 10 days to complete a job working 12 hours a day.How many hours a day should 10 men work to complete the job in 20 days ?

Video Solution
Text Solution
Verified by Experts

Since 15 men take 10 days working 12 hours per day, the total work done measured in terms of man-hours is 15×1012.
When 10 men are required to complete the same job in 20 days working h hours a day, work done =10×20×h. But 10×20×h=15×10×12. Hence the number of hours for which they should work per day is 15×10×1210×20=9.
10 men can complete the work in 20 days working for 9 hours per day.
Hence, in general we can say that:
If M1 men can do W1 units of work in D1 days working H1 hours per day and M2 men can do
W2 untis of work in D2 days working H2 hours per day, then M1D1H1W1=M2D2H2W2

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    15 men take 20 days to com plete a job working 8 hours a day. The number of hours a day should 20 men take to complete the job in 12 days

    A5 hours
    B10 hours
    C15 hours
    D18 hours
  • Question 2 - Select One

    Fifteen men take 30 days to complete a piece of work, working 8 hours a day. Find the time taken by 30 men to complete 5 times as much work, working 10 hours a day.

    A30 days
    B45 days
    C60 days
    D15 days
  • Question 3 - Select One

    Fifteen men take 30 days to complete a piece of work, working 8 hours a day. Find the time taken by 30 men to complete 5 times as much work, working 10 hours a day.

    A30 days
    B45 days
    C60 days
    D15 days