Doubtnut Promotions Sticky

A can do a piece of work in 20 days while B can do it in 30 days. Both of them start the work together and work for some time, then B leaves. If A completes the remaining work in 10 days, then find the number of days for which they worked together.

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:6


To solve the problem step by step, we will calculate the amount of work done by A and B, and then determine how long they worked together before B left.

Step 1: Calculate the work rates of A and B
- A can complete the work in 20 days, so A's work rate is:
Work rate of A=120 (work per day)
- B can complete the work in 30 days, so B's work rate is:
Work rate of B=130 (work per day)

Step 2: Calculate the combined work rate of A and B
- When A and B work together, their combined work rate is:
Combined work rate=120+130
- To add these fractions, find a common denominator. The least common multiple of 20 and 30 is 60:
120=360,130=260
- Therefore, the combined work rate is:
Combined work rate=360+260=560=112 (work per day)

Step 3: Determine the total work done by A in 10 days
- A completes the remaining work in 10 days. Since A's work rate is 120, the amount of work A does in 10 days is:
Work done by A in 10 days=10×120=1020=12 of the total work

Step 4: Calculate the total work
- If A completed 12 of the total work in 10 days, then the total work can be represented as:
Total work=1 (whole work)

Step 5: Determine the work done before B leaves
- Since A completed 12 of the work alone, the other half must have been completed by A and B together. Thus, the work done by A and B together is:
Work done by A and B together=112=12

Step 6: Calculate the time they worked together
- Let T be the number of days they worked together. The work done by A and B together in T days is:
T×112=12
- Solving for T:
T=1/21/12=12×121=6 days

Final Answer
- A and B worked together for 6 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it?

    A70 days
    B4234 days
    C2717days
    D1717 days
  • Question 2 - Select One

    A can do a piece of work in 14 days while B can do it in 28 days. In how many days, working together will they complete the whole work?

    A10.5
    B8
    C283
    D9
  • Question 3 - Select One

    A can do a piece of work in 14 days while B can do it in 21 days. In how many days, working together they will complete the whole work?

    A10.5
    B8
    C8.4
    D9