A can do a piece of work in 20 days while B can do it in 30 days. Both of them start the work together and work for some time, then B leaves. If A completes the remaining work in 10 days, then find the number of days for which they worked together.
The correct Answer is:6
To solve the problem, we will follow these steps:
Step 1: Calculate the work done by A and B in one day.
- A can complete the work in 20 days, so A's work rate is 120 of the work per day.
- B can complete the work in 30 days, so B's work rate is 130 of the work per day.
Step 2: Calculate the combined work rate of A and B.
- The combined work rate of A and B when they work together is:
Combined work rate=120+130
- To add these fractions, we need a common denominator. The least common multiple of 20 and 30 is 60.
- Converting the fractions:
120=360,130=260
- Now adding them:
Combined work rate=360+260=560=112
- This means A and B together can complete 112 of the work in one day.
Step 3: Determine the amount of work A completes alone in 10 days.
- After B leaves, A completes the remaining work in 10 days.
- The amount of work A can complete in 10 days is:
Work done by A in 10 days=10×120=1020=12
- This means A completes half of the total work alone.
Step 4: Calculate the total work done before B leaves.
- Since A completed 12 of the work alone, the remaining work done by A and B together before B left is also 12.
- Let x be the number of days they worked together. The work done by A and B together in x days is:
Work done together=x×112
- Setting this equal to the remaining work:
x×112=12
Step 5: Solve for x.
- To find x, we can multiply both sides by 12:
x=12×12=6
Conclusion:
- Therefore, A and B worked together for 6 days.
- A can complete the work in 20 days, so A's work rate is 120 of the work per day.
- B can complete the work in 30 days, so B's work rate is 130 of the work per day.
- The combined work rate of A and B when they work together is:
Combined work rate=120+130
- To add these fractions, we need a common denominator. The least common multiple of 20 and 30 is 60.
- Converting the fractions:
120=360,130=260
- Now adding them:
Combined work rate=360+260=560=112
- This means A and B together can complete 112 of the work in one day.
- After B leaves, A completes the remaining work in 10 days.
- The amount of work A can complete in 10 days is:
Work done by A in 10 days=10×120=1020=12
- This means A completes half of the total work alone.
- Since A completed 12 of the work alone, the remaining work done by A and B together before B left is also 12.
- Let x be the number of days they worked together. The work done by A and B together in x days is:
Work done together=x×112
- Setting this equal to the remaining work:
x×112=12
- To find x, we can multiply both sides by 12:
x=12×12=6
- Therefore, A and B worked together for 6 days.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - Essay Type Question5videos
TIME AND WORK PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-1)33videos
TIME AND WORK PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - TEST YOUR CONCEPTS (Very Short Answer Type Questions)30videos
TIME AND WORK PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND DISTANCE EXERCISE - Concept Application (Level 2 )3videos
TIME AND DISTANCE
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)7videos
TIME AND WORK, PIPES AND CISTERNS
Similar Questions
A can do a piece of work in 20 days while B can do it in 30 days. Both of them start the work together and work for some time, then B leaves. If A completes the remaining work in 10 days, then find the number of days for which they worked together.
View SolutionRajan can do a piece of work in 24 days while Amit can do it in 30 days. In how many days can they complete it they work together?
View Solution
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it?
A70 daysB4234 daysC2717daysD1717 days - Question 2 - Select One
A can do a piece of work in 14 days while B can do it in 28 days. In how many days, working together will they complete the whole work?
A10.5B8C283D9 - Question 3 - Select One
A can do a piece of work in 14 days while B can do it in 21 days. In how many days, working together they will complete the whole work?
A10.5B8C8.4D9
A can do a piece of work in 20 days and B can do same work in 15 days. Both A and B start the work and after some days B left and A complete the remaining work in 6 days. After how many days will B left work?
View SolutionA can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?
View SolutionA can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :
View SolutionA can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in
View SolutionA can do a piece of work in 10 days and B can dothe same piece of work in 20 days. They start the work together but after 5 days A leaves off. B will do the remaining piece of work in..
View Solution