Doubtnut Promotions Sticky

A can do a piece of work in 20 days and B can do same work in 15 days. Both A and B start the work and after some days B left and A complete the remaining work in 6 days. After how many days will B left work?

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:6 days


To solve the problem step by step, we will follow the reasoning laid out in the video transcript.

Step 1: Determine the total work
Let’s assume the total work is the least common multiple (LCM) of the days A and B take to complete the work. A can complete the work in 20 days and B in 15 days.

Calculation:
- LCM of 20 and 15 = 60 units

Step 2: Calculate the work done by A and B in one day
Now we can find out how much work A and B can do in one day.

For A:
- A's work in one day = Total work / Days taken by A = 60 / 20 = 3 units per day

For B:
- B's work in one day = Total work / Days taken by B = 60 / 15 = 4 units per day

Step 3: Determine the work done by A in 6 days
According to the question, after B leaves, A completes the remaining work in 6 days. We need to find out how much work A does in those 6 days.

Calculation:
- Work done by A in 6 days = A's work per day * 6 = 3 * 6 = 18 units

Step 4: Calculate the remaining work after A's 6 days of work
Now, we can find out how much work is left after A has completed his part in 6 days.

Calculation:
- Remaining work = Total work - Work done by A in 6 days = 60 - 18 = 42 units

Step 5: Set up the equation for the work done by A and B together
Let T be the number of days A and B worked together before B left. The total work done by A and B together is equal to the remaining work.

Equation:
- Work done by A and B together = (A's efficiency + B's efficiency) * T
- 42 = (3 + 4) * T
- 42 = 7T

Step 6: Solve for T
Now we can solve for T.

Calculation:
- T = 42 / 7 = 6 days

Conclusion
B left the work after 6 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    (A + B) can do a piece of work in 12 days. (B + C) can do same work in 623 days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?

    A18,15.,20
    B30,20,10
    C10,15,25
    D15,10,25
  • Question 2 - Select One

    A can do a piece of work in 10 days and B can do it in 15 days. After they have worked together for 4 days, A does away and B completes the remaining work. In how many days B complete the remaining work ?

    A10
    B5
    C15
    D20
  • Question 3 - Select One

    A can do a work in 20 days and B can do the same work in 30 days in how many days canA and B together do the work?

    A15
    B16
    C10
    D12