A can do a piece of work in 10 days and B can do it in 15 days. After they have worked together for 4 days, A does away and B completes the remaining work. In how many days B complete the remaining work ?
10
5
15
20
The correct Answer is:B
To solve the problem step by step, we will follow these calculations:
Step 1: Determine the work done by A and B in one day.
- A can complete the work in 10 days. Therefore, A's work in one day is:
Work done by A in one day=110 of the work
- B can complete the work in 15 days. Therefore, B's work in one day is:
Work done by B in one day=115 of the work
Step 2: Find a common unit of work.
- To make calculations easier, we can assume the total work is 30 units (the least common multiple of 10 and 15).
- Thus, A's work in one day:
A's work=3010=3 units
- B's work in one day:
B's work=3015=2 units
Step 3: Calculate the combined work of A and B in one day.
- Together, A and B can do:
Combined work=3+2=5 units
Step 4: Calculate the work done by A and B together in 4 days.
- In 4 days, the total work done by A and B is:
Work done in 4 days=4×5=20 units
Step 5: Determine the remaining work.
- The total work is 30 units, and they have completed 20 units together. Therefore, the remaining work is:
Remaining work=30−20=10 units
Step 6: Calculate how long it will take B to finish the remaining work.
- B can do 2 units of work in one day. To find out how many days B will take to finish the remaining 10 units, we calculate:
Days taken by B=Remaining workB's work in one day=102=5 days
Conclusion
B will take 5 days to complete the remaining work.
---
- A can complete the work in 10 days. Therefore, A's work in one day is:
Work done by A in one day=110 of the work
- B can complete the work in 15 days. Therefore, B's work in one day is:
Work done by B in one day=115 of the work
- To make calculations easier, we can assume the total work is 30 units (the least common multiple of 10 and 15).
- Thus, A's work in one day:
A's work=3010=3 units
- B's work in one day:
B's work=3015=2 units
- Together, A and B can do:
Combined work=3+2=5 units
- In 4 days, the total work done by A and B is:
Work done in 4 days=4×5=20 units
- The total work is 30 units, and they have completed 20 units together. Therefore, the remaining work is:
Remaining work=30−20=10 units
- B can do 2 units of work in one day. To find out how many days B will take to finish the remaining 10 units, we calculate:
Days taken by B=Remaining workB's work in one day=102=5 days
B will take 5 days to complete the remaining work.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-2)20videos
TIME AND WORK PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)7videos
TIME AND WORK PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - Essay Type Question5videos
TIME AND WORK PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND DISTANCE EXERCISE - Concept Application (Level 2 )3videos
TIME AND DISTANCE
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)7videos
TIME AND WORK, PIPES AND CISTERNS
Similar Questions
A can do a piece of work in 40 days and B in 45 days.They work together for 10 days and then B goes away. In how many days will A finish the remaining work?
View SolutionA can do a piece of work in 25 days and B can finish it in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?
View Solution
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 10 days and B can do it in 15 days. After they have worked together for 4 days, A does away and B completes the remaining work. In how many days B complete the remaining work ?
A10B5C15D20 - Question 2 - Select One
A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :
A9B8C10D6 - Question 3 - Select One
A can finish a work in 12 days and B can do it in 15 days. ’After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?
A5B512C412D6
A can do a piece of work in 14 days while B can do it in 21 days. They began together and worked at it for 6 days. Then A fell ill and B had to complete the remaining work alone. In how many days was the work completed?
View SolutionA can finish a work in 12 days and B can do it in 15 days. After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?
View SolutionA can finish a work in 12 days and B can do it in 15 days. ’After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?
View SolutionA can do a piece of work in 25 days and B in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?
View SolutionA can do a piece of work in 12 days and B in 15 days. They work together for 5 days and then B left. The days taken by A to finish the remaining work is
View Solution