Doubtnut Promotions Sticky

A can do a piece of work in 10 days and B can do it in 15 days. After they have worked together for 4 days, A does away and B completes the remaining work. In how many days B complete the remaining work ?

A

10

B

5

C

15

D

20

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will follow these calculations:

Step 1: Determine the work done by A and B in one day.
- A can complete the work in 10 days. Therefore, A's work in one day is:
Work done by A in one day=110 of the work
- B can complete the work in 15 days. Therefore, B's work in one day is:
Work done by B in one day=115 of the work

Step 2: Find a common unit of work.
- To make calculations easier, we can assume the total work is 30 units (the least common multiple of 10 and 15).
- Thus, A's work in one day:
A's work=3010=3 units
- B's work in one day:
B's work=3015=2 units

Step 3: Calculate the combined work of A and B in one day.
- Together, A and B can do:
Combined work=3+2=5 units

Step 4: Calculate the work done by A and B together in 4 days.
- In 4 days, the total work done by A and B is:
Work done in 4 days=4×5=20 units

Step 5: Determine the remaining work.
- The total work is 30 units, and they have completed 20 units together. Therefore, the remaining work is:
Remaining work=3020=10 units

Step 6: Calculate how long it will take B to finish the remaining work.
- B can do 2 units of work in one day. To find out how many days B will take to finish the remaining 10 units, we calculate:
Days taken by B=Remaining workB's work in one day=102=5 days

Conclusion
B will take 5 days to complete the remaining work.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a piece of work in 10 days and B can do it in 15 days. After they have worked together for 4 days, A does away and B completes the remaining work. In how many days B complete the remaining work ?

    A10
    B5
    C15
    D20
  • Question 2 - Select One

    A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :

    A9
    B8
    C10
    D6
  • Question 3 - Select One

    A can finish a work in 12 days and B can do it in 15 days. ’After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?

    A5
    B512
    C412
    D6