Doubtnut Promotions Sticky

A,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?

A

5

B

4

C

3

D

6

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will first determine the work done by A, B, and C in one day, then calculate the total work done by A and B, and finally find out how many days C will take to complete the remaining work.

1. Determine the Work Rates:
- A can complete the work in 12 days, so A's one day work = 112.
- B can complete the work in 18 days, so B's one day work = 118.
- C can complete the work in 9 days, so C's one day work = 19.

2. Calculate Work Done by A in 4 Days:
- Work done by A in 4 days = 4×112=412=13.

3. Calculate Work Done by B in 2 Days:
- Work done by B in 2 days = 2×118=218=19.

4. Calculate Total Work Done by A and B:
- Total work done by A and B = Work done by A + Work done by B
- Total work = 13+19.
- To add these fractions, find a common denominator (which is 9):
- 13=39
- So, 13+19=39+19=49.

5. Calculate Remaining Work:
- Total work = 1 (the whole work).
- Remaining work = Total work - Work done by A and B
- Remaining work = 149=59.

6. Calculate Days Required by C to Complete Remaining Work:
- C's one day work = 19.
- Let x be the number of days C will take to complete the remaining work.
- Work done by C in x days = x×19.
- Set this equal to the remaining work:
- x×19=59.
- Multiply both sides by 9:
- x=5.

Final Answer:
C will take 5 days to complete the remaining work.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can do a piece of work in 24 and 30 days respectively.
    Both started the work and worked for 6 days. Then B leaves
    the work and C joins and the remaining work is completed by A and C together in 11 days. Find the days in which C
    alone can do the work

    A80
    B100
    C120
    D130
  • Question 2 - Select One

    A, b and C can alone complete a work in 10, 12 and 15 days
    respectively. A and C started the work and after working for
    4 days, A left and B joined. In how many days the total work
    was completed ?

    A659days
    B629days
    C6 days
    D549days
  • Question 3 - Select One

    A, B and C, one can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed?

    A2
    B52
    C114
    D95