A,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?
5
4
3
6
The correct Answer is:A
To solve the problem step by step, we will first determine the work done by A, B, and C in one day, then calculate the total work done by A and B, and finally find out how many days C will take to complete the remaining work.
1. Determine the Work Rates:
- A can complete the work in 12 days, so A's one day work = 112.
- B can complete the work in 18 days, so B's one day work = 118.
- C can complete the work in 9 days, so C's one day work = 19.
2. Calculate Work Done by A in 4 Days:
- Work done by A in 4 days = 4×112=412=13.
3. Calculate Work Done by B in 2 Days:
- Work done by B in 2 days = 2×118=218=19.
4. Calculate Total Work Done by A and B:
- Total work done by A and B = Work done by A + Work done by B
- Total work = 13+19.
- To add these fractions, find a common denominator (which is 9):
- 13=39
- So, 13+19=39+19=49.
5. Calculate Remaining Work:
- Total work = 1 (the whole work).
- Remaining work = Total work - Work done by A and B
- Remaining work = 1−49=59.
6. Calculate Days Required by C to Complete Remaining Work:
- C's one day work = 19.
- Let x be the number of days C will take to complete the remaining work.
- Work done by C in x days = x×19.
- Set this equal to the remaining work:
- x×19=59.
- Multiply both sides by 9:
- x=5.
Final Answer:
C will take 5 days to complete the remaining work.
- A can complete the work in 12 days, so A's one day work = 112.
- B can complete the work in 18 days, so B's one day work = 118.
- C can complete the work in 9 days, so C's one day work = 19.
- Work done by A in 4 days = 4×112=412=13.
- Work done by B in 2 days = 2×118=218=19.
- Total work done by A and B = Work done by A + Work done by B
- Total work = 13+19.
- To add these fractions, find a common denominator (which is 9):
- 13=39
- So, 13+19=39+19=49.
- Total work = 1 (the whole work).
- Remaining work = Total work - Work done by A and B
- Remaining work = 1−49=59.
- C's one day work = 19.
- Let x be the number of days C will take to complete the remaining work.
- Work done by C in x days = x×19.
- Set this equal to the remaining work:
- x×19=59.
- Multiply both sides by 9:
- x=5.
C will take 5 days to complete the remaining work.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-2)20videos
TIME AND WORK PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)7videos
TIME AND WORK PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - Essay Type Question5videos
TIME AND WORK PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND DISTANCE EXERCISE - Concept Application (Level 2 )3videos
TIME AND DISTANCE
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)7videos
TIME AND WORK, PIPES AND CISTERNS
Similar Questions
A, B and C can do a piece of work in 15, 12 and 20 days respectively. They started the work together, but C left after 2 days. In how many days will the remaining work be completed by A and B?
View SolutionA and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work ?
View Solution
Knowledge Check
- Question 1 - Select One
A and B can do a piece of work in 24 and 30 days respectively.
Both started the work and worked for 6 days. Then B leaves
the work and C joins and the remaining work is completed by A and C together in 11 days. Find the days in which C
alone can do the workA80B100C120D130 - Question 2 - Select One
A, b and C can alone complete a work in 10, 12 and 15 days
respectively. A and C started the work and after working for
4 days, A left and B joined. In how many days the total work
was completed ?A659daysB629daysC6 daysD549days - Question 3 - Select One
A, B and C, one can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed?
A2B52C114D95
A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?
View SolutionA can complete of a work in 8 days. B can complete35 of the same work in 12 days and C can complete 49 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?
View SolutionA and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?
View SolutionA and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?
View SolutionA and B can do a job in 16 days and 12 days respectively. B has started the work alone 4 days before finishing the job, A joins B. How many days has B worked alone?
View Solution