Doubtnut Promotions Sticky

45 people take 18 days to dig a pond. If the pond would have to be dug in 15 days, then the number of people to be employed will be

A

50

B

54

C

60

D

72

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:B

|
Answer

Step by step video, text & image solution for 45 people take 18 days to dig a pond. If the pond would have to be dug in 15 days, then the number of people to be employed will be by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Related Playlists


Similar Practice Problems

  • Question 1 - Select One

    A contractor undertook to do a piece of work in 9 days. He employed certain number of laboures but 6 of them were absent from the very first day and the rest could finish the work in only 15 days. Find the number of men originally employed

    A15
    B6
    C13
    D9
  • Question 1 - Select One

    Six people i.e. Q, W, K, U, R and L have meeting on different days of the same week starting from Monday and ends on Saturday. K has meeting just after Q but not on Thursday. Not more than two people have meeting after R. Three people have meeting between R and W. The number of people have meeting after W is same as the number of people have meeting before U. How many people have meeting before L?

    ATwo
    BOne
    CThree
    DFour
  • Question 1 - Select One

    A contractor undertook to do a certain piece of work in 18 days. He employed certain number of men but 12 of them being absent from the very 1st day , the rest could finish the work in 30 days . Find the number of men originally employed .

    A40
    B15
    C45
    D30
  • Question 1 - Select One

    There was a leakage in the container of the refined oil. If 11 kg oil is leaked out per day then it would have lasted for 50 days, if the leakage was 15 kg per day, then it would have lasted for only 45 days. For how many days would the oil have lasted, if there was no leakage and it was completely used for eating purpose?

    A80 days
    B72 days
    C100 days
    D120 days
  • Question 1 - Select One

    The following table gives zonewise survey report of the people of a country who take coffee. Study the table and answer the questions.
    ocr_image
    The ratio of the total number of people surveyed who take coffee more than 3 times a day to the total number of people who do not take coffee at all is

    A1:1.4
    B1.4:1
    C1.5:1
    D1:1.1
  • Question 1 - Select One

    450 man-days of work can be completed by a certain number of men in some days. If the number of people (men) are increased by 27, then the. number of day required to complete the same work is decreased- by 15. The number of days are required to complete the" three times work (than the previous/actual work) by 27 men?

    A50
    B60
    C54
    D45
  • Question 1 - Select One

    450 man-days of work can be completed by a certain number of men in some days. If the number of people (men) are increased by 27, then the. number of day required to complete the same work is decreased- by 15. The number of days are required to complete the" three times work (than the previous/actual work) by 27 men?

    A50
    B60
    C54
    D45
  • Question 1 - Select One

    A can complete a task alone in 9 days while B takes 13.5 days to do it by herself . Together with C it takes them 4.5 days to complete the task . If C and D together can complete the task in 18 days , then how many days will D need to complete the task by herself ?

    A60
    B54
    C48
    D45

Similar Questions