Doubtnut Promotions Sticky

45 people take 18 days to dig a pond. If the pond would have to be dug in 15 days, then the number of people to be employed will be

A

50

B

54

C

60

D

72

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we can use the concept of work done, which is based on the formula:

Work=Number of People×Number of Days

Given:
- M1=45 (initial number of people)
- D1=18 (initial number of days)
- M2=? (number of people needed)
- D2=15 (new number of days)

Step 1: Calculate the total work done in terms of person-days.
The total work done to dig the pond can be calculated using the initial number of people and the number of days they worked.

Total Work=M1×D1=45×18

Step 2: Calculate the total work.
Now, let's calculate the total work:

Total Work=45×18=810 person-days

Step 3: Set up the equation for the new scenario.
In the new scenario, we need to find out how many people are required to complete the same amount of work in 15 days. We can set up the equation as follows:

Total Work=M2×D2

Substituting the known values:

810=M2×15

Step 4: Solve for M2.
Now, we can solve for M2:

M2=81015

Step 5: Calculate M2.
Now, let's calculate M2:

M2=81015=54

Conclusion:
Therefore, the number of people that need to be employed to dig the pond in 15 days is M2=54.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A contractor undertook to do a piece of work in 9 days. He employed certain number of laboures but 6 of them were absent from the very first day and the rest could finish the work in only 15 days. Find the number of men originally employed

    A15
    B6
    C13
    D9
  • Question 2 - Select One

    Six people i.e. Q, W, K, U, R and L have meeting on different days of the same week starting from Monday and ends on Saturday. K has meeting just after Q but not on Thursday. Not more than two people have meeting after R. Three people have meeting between R and W. The number of people have meeting after W is same as the number of people have meeting before U. How many people have meeting before L?

    ATwo
    BOne
    CThree
    DFour
  • Question 3 - Select One

    A contractor undertook to do a certain piece of work in 18 days. He employed certain number of men but 12 of them being absent from the very 1st day , the rest could finish the work in 30 days . Find the number of men originally employed .

    A40
    B15
    C45
    D30