45 people take 18 days to dig a pond. If the pond would have to be dug in 15 days, then the number of people to be employed will be
50
54
60
72
The correct Answer is:B
To solve the problem step by step, we can use the concept of work done, which is based on the formula:
Work=Number of People×Number of Days
Given:
- M1=45 (initial number of people)
- D1=18 (initial number of days)
- M2=? (number of people needed)
- D2=15 (new number of days)
Step 1: Calculate the total work done in terms of person-days.
The total work done to dig the pond can be calculated using the initial number of people and the number of days they worked.
Total Work=M1×D1=45×18
Step 2: Calculate the total work.
Now, let's calculate the total work:
Total Work=45×18=810 person-days
Step 3: Set up the equation for the new scenario.
In the new scenario, we need to find out how many people are required to complete the same amount of work in 15 days. We can set up the equation as follows:
Total Work=M2×D2
Substituting the known values:
810=M2×15
Step 4: Solve for M2.
Now, we can solve for M2:
M2=81015
Step 5: Calculate M2.
Now, let's calculate M2:
M2=81015=54
Conclusion:
Therefore, the number of people that need to be employed to dig the pond in 15 days is M2=54.
---
- M1=45 (initial number of people)
- D1=18 (initial number of days)
- M2=? (number of people needed)
- D2=15 (new number of days)
The total work done to dig the pond can be calculated using the initial number of people and the number of days they worked.
Now, let's calculate the total work:
In the new scenario, we need to find out how many people are required to complete the same amount of work in 15 days. We can set up the equation as follows:
Now, we can solve for M2:
Now, let's calculate M2:
Therefore, the number of people that need to be employed to dig the pond in 15 days is M2=54.
Topper's Solved these Questions
- BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION16videos
WORK AND TIME
- BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION16videos
WORK AND TIME
- BOOK - ARIHANT SSCCHAPTER - VOLUME AND SURFACE AREA EXERCISE - FAST TRACK PRACTICE111videos
VOLUME AND SURFACE AREA
- BOOK - ARIHANT SSCCHAPTER - WORK AND WAGES EXERCISE - EXERCISE (HIGHER SKILL LEVEL QUESTIONS)7videos
WORK AND WAGES
Similar Questions
Knowledge Check
- Question 1 - Select One
A contractor undertook to do a piece of work in 9 days. He employed certain number of laboures but 6 of them were absent from the very first day and the rest could finish the work in only 15 days. Find the number of men originally employed
A15B6C13D9 - Question 2 - Select One
Six people i.e. Q, W, K, U, R and L have meeting on different days of the same week starting from Monday and ends on Saturday. K has meeting just after Q but not on Thursday. Not more than two people have meeting after R. Three people have meeting between R and W. The number of people have meeting after W is same as the number of people have meeting before U. How many people have meeting before L?
ATwoBOneCThreeDFour - Question 3 - Select One
A contractor undertook to do a certain piece of work in 18 days. He employed certain number of men but 12 of them being absent from the very 1st day , the rest could finish the work in 30 days . Find the number of men originally employed .
A40B15C45D30
There was a leakage in the container of the refined oil. If 11 kg oil is leaked out per day then it would have lasted for 50 days, if the leakage was 15 kg per day, then it would have lasted for only 45 days. For how many days would the oil have lasted, if there was no leakage and it was completely used for eating purpose?
View SolutionThe following table gives zonewise survey report of the people of a country who take coffee. Study the table and answer the questions.
The ratio of the total number of people surveyed who take coffee more than 3 times a day to the total number of people who do not take coffee at all isView Solution450 man-days of work can be completed by a certain number of men in some days. If the number of people (men) are increased by 27, then the. number of day required to complete the same work is decreased- by 15. The number of days are required to complete the" three times work (than the previous/actual work) by 27 men?
View Solution450 man-days of work can be completed by a certain number of men in some days. If the number of people (men) are increased by 27, then the. number of day required to complete the same work is decreased- by 15. The number of days are required to complete the" three times work (than the previous/actual work) by 27 men?
View SolutionA can complete a task alone in 9 days while B takes 13.5 days to do it by herself . Together with C it takes them 4.5 days to complete the task . If C and D together can complete the task in 18 days , then how many days will D need to complete the task by herself ?
View Solution