16 children and 24 men complete a certain workin 18days. If each child takes twice the time taken by a man to finish the work, in how many days will 24 men finish the same work?

A

12 days

B

24 days

C

36 days

D

48 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step-by-step, we need to analyze the given information and apply the concepts of work and time.

Step 1: Understand the Work Done by Children and Men
We know that 16 children and 24 men complete a certain work in 18 days.

Step 2: Establish the Relationship Between the Time Taken by Children and Men
It is given that each child takes twice the time taken by a man to finish the work. Therefore, if we denote the time taken by a man to complete the work as T, then the time taken by a child will be 2T.

Step 3: Determine the Efficiency Ratio
Since work is inversely proportional to time, the efficiency ratio of children to men can be established as follows:
- If one man's efficiency is M, then one child's efficiency will be M2 because a child takes twice as long.

Thus, the efficiency ratio of children to men is:
Efficiency of 1 child=M2,Efficiency of 1 man=M
This gives us the ratio:
Efficiency of 1 childEfficiency of 1 man=12

Step 4: Calculate Total Efficiency of Children and Men
Now, we can calculate the total efficiency of 16 children and 24 men:
- Total efficiency of 16 children = 16×M2=8M
- Total efficiency of 24 men = 24×M=24M

Adding these together:
Total efficiency=8M+24M=32M

Step 5: Calculate Total Work Done
The total work done can be calculated using the formula:
Total Work=Total Efficiency×Time
Substituting the values we have:
Total Work=32M×18=576M

Step 6: Calculate the Time Taken by 24 Men to Complete the Same Work
Now, we need to find out how many days X it will take for 24 men to complete the same work. The efficiency of 24 men is:
Efficiency of 24 men=24M
Using the total work calculated:
Total Work=Efficiency of 24 men×Time taken by 24 men
Thus:
576M=24M×X

Step 7: Solve for X
Now, we can solve for X:
X=576M24M=57624=24

Conclusion
Thus, 24 men will take 24 days to complete the same work.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • 6 children and 2 men complete a certain piece of work in 6 days. Each child takes twice the time taken by a man to finish the work In how many days will 5 men finish the same work?

    A6
    B8
    C9
    D15
  • 8 children and 12 men complete a certain piece of work in 9 days. Each child takes twice the time taken by a man to finish the work. In how many days will 12 men finish the same work?

    A8
    B15
    C9
    D12
  • 6 children and 2 men complete a certain piece of work in 6 days. Each child takes twice the time taken by a man to finish the work. In how many days will 5 men finish the same work?

    A6
    B8
    C9
    D15