25 men and 15 women can complete a piece of work in 12 days. All of them start working together and after working for 8 days, the women stopped working 25 men completed the remaining work in 6 days. How many days will it take for completing the entire job, if only 15 women are put on the job?
48 days
24 days
36 days
60 days
The correct Answer is:C
To solve the problem step by step, we will follow the logical sequence of calculations based on the information provided.
Step 1: Determine the total work done by 25 men and 15 women in 12 days.
Let the efficiency of one man be M and the efficiency of one woman be W.
The total work done by 25 men and 15 women in 12 days can be expressed as:
Total Work=(25M+15W)×12
Step 2: Calculate the work done in the first 8 days by both men and women.
In the first 8 days, all 25 men and 15 women worked together:
Work done in 8 days=(25M+15W)×8
Step 3: Determine the remaining work after 8 days.
After 8 days, the remaining work is:
Remaining Work=Total Work−Work done in 8 days
Step 4: Calculate the work done by 25 men in the next 6 days.
After the first 8 days, only the 25 men continue to work for 6 more days:
Work done by 25 men in 6 days=25M×6
Step 5: Set up the equation for total work.
Now, we can equate the total work done to the sum of the work done in the first 8 days and the work done in the next 6 days:
(25M+15W)×12=(25M+15W)×8+25M×6
Step 6: Simplify the equation.
Expanding both sides:
300M+180W=200M+120W+150M
300M+180W=350M+120W
Step 7: Rearranging the equation.
Rearranging gives:
180W−120W=350M−300M
60W=50M
Step 8: Find the ratio of women's efficiency to men's efficiency.
From the equation 60W=50M:
WM=5060=56
This means the efficiency of one woman is 5 and the efficiency of one man is 6.
Step 9: Calculate the total work done.
Now, we can calculate the total work done:
Total Work=(25×6+15×5)×12
Calculating the efficiencies:
=(150+75)×12=225×12=2700 units of work
Step 10: Determine how long it will take for 15 women to complete the work.
The efficiency of 15 women is:
15W=15×5=75 units of work per day
Now, to find the number of days D it will take for 15 women to complete the total work:
D=Total WorkEfficiency of 15 women=270075=36 days
Final Answer:
It will take 36 days for 15 women to complete the entire job.
---
Total Work=(25M+15W)×12
Work done in 8 days=(25M+15W)×8
Remaining Work=Total Work−Work done in 8 days
Work done by 25 men in 6 days=25M×6
(25M+15W)×12=(25M+15W)×8+25M×6
300M+180W=200M+120W+150M
300M+180W=350M+120W
180W−120W=350M−300M
60W=50M
WM=5060=56
Total Work=(25×6+15×5)×12
Calculating the efficiencies:
=(150+75)×12=225×12=2700 units of work
15W=15×5=75 units of work per day
D=Total WorkEfficiency of 15 women=270075=36 days
It will take 36 days for 15 women to complete the entire job.
Topper's Solved these Questions
- PRACTICE SET Book:ARIHANT SSCChapter:PRACTICE SET Exercise:PRACTICE SET-5
Explore 50 Videos
- PRACTICE SET Book:ARIHANT SSCChapter:PRACTICE SET Exercise:PRACTICE SET-3
Explore 50 Videos
- PIPES AND CISTERNS Book:ARIHANT SSCChapter:PIPES AND CISTERNS Exercise:EXERCISE HIGHER SKILL LEVEL QUESTION
Explore 17 Videos
- PROBABILITYBook:ARIHANT SSCChapter:PROBABILITYExercise:EXERCISE (LEVEL-2)
Explore 19 Videos
Similar Questions
Three men or five women can complete a piece of work in 8 days. In how many days can 6 men and 6 women complete it?
View SolutionThree men can complete a plece of work in 6 days. Two days after they started the work, 3 more men joined them. How many days will they take to complete the remaining work?
View Solution
Knowledge Check
25 men and 15 women can complete the work in 12 days. They started working together and after 8 days, women left the work. Now 25 men complete the remaining work in 6 days. Find the time required to complete the work by only 15 women?
A36 daysB88 daysC94 daysDNone of these9 women con complete a piece of work in 19 days. How
many days will 18 women take to complete the same piece of
work ?A12 daysB6.5 daysC9 daysDNone of these15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
A40B42C38D32
20 women can complete a piece of work in 7 days. If 8 more women are put on the job. In how many days will they complete the work?
View Solution20 men or 24 women can complete a piece of work in 20 days. If 30 men and 112 women under take to complete the work, the work will be completed in:
View SolutionA can complete a piece of work in 25 days. After working for 5 days, remaining work is completed in 15 days with the help of B. Then B can complete the whole work in how many days?
View Solution12 men and 15 women can complete a work in 10 days. In how many days the same work will be completed by 7 men and 10 women?
View Solution20 men or 24 women can complete a piece of work in 20 days. If 30 men and 112 women under take to complete the work, the work will be completed in:
View Solution