20 men or 24 women can complete a piece of work in 20 days. If 30 men and 112 women under take to complete the work, the work will be completed in:
10 days
12 days
15 days
16 days
The correct Answer is:A
To solve the problem step-by-step, we will first determine the work done by men and women, and then calculate how long it will take for 30 men and 12 women to complete the work.
Step 1: Determine the work done by men and women
The problem states that 20 men or 24 women can complete the work in 20 days.
- Work done by 20 men in 20 days = 1 unit of work
- Therefore, the work done by 1 man in 20 days = 1/20 units of work
- Hence, the work done by 1 man in 1 day = 1/400 units of work (since 20 days are considered)
For women:
- Work done by 24 women in 20 days = 1 unit of work
- Therefore, the work done by 1 woman in 20 days = 1/24 units of work
- Hence, the work done by 1 woman in 1 day = 1/480 units of work (since 20 days are considered)
Step 2: Establish the relationship between men and women
From the information provided:
- 20 men = 24 women
- This can be simplified to find the relationship between the work done by men and women:
5 men=6 women
Thus, the efficiency of 1 man can be expressed in terms of women:
- 1 man = (6/5) women
Step 3: Calculate the efficiency of 30 men and 12 women
Now, we need to calculate the total efficiency of 30 men and 12 women.
1. Efficiency of 30 men:
- 30 men = 30 * (1/400) = 30/400 = 3/40 units of work per day
2. Efficiency of 12 women:
- 12 women = 12 * (1/480) = 12/480 = 1/40 units of work per day
3. Total efficiency:
- Total efficiency = Efficiency of men + Efficiency of women
- Total efficiency = (3/40) + (1/40) = 4/40 = 1/10 units of work per day
Step 4: Calculate the time taken to complete the work
Since the total efficiency of 30 men and 12 women is 1/10 units of work per day, we can find the time taken to complete 1 unit of work:
- Time taken = Total work / Total efficiency
- Time taken = 1 / (1/10) = 10 days
Conclusion
Thus, 30 men and 12 women can complete the work in 10 days.
The problem states that 20 men or 24 women can complete the work in 20 days.
- Therefore, the work done by 1 man in 20 days = 1/20 units of work
- Hence, the work done by 1 man in 1 day = 1/400 units of work (since 20 days are considered)
- Work done by 24 women in 20 days = 1 unit of work
- Therefore, the work done by 1 woman in 20 days = 1/24 units of work
- Hence, the work done by 1 woman in 1 day = 1/480 units of work (since 20 days are considered)
From the information provided:
- 20 men = 24 women
- This can be simplified to find the relationship between the work done by men and women:
5 men=6 women
- 1 man = (6/5) women
Now, we need to calculate the total efficiency of 30 men and 12 women.
- 30 men = 30 * (1/400) = 30/400 = 3/40 units of work per day
- 12 women = 12 * (1/480) = 12/480 = 1/40 units of work per day
- Total efficiency = Efficiency of men + Efficiency of women
- Total efficiency = (3/40) + (1/40) = 4/40 = 1/10 units of work per day
Since the total efficiency of 30 men and 12 women is 1/10 units of work per day, we can find the time taken to complete 1 unit of work:
- Time taken = 1 / (1/10) = 10 days
Thus, 30 men and 12 women can complete the work in 10 days.
Topper's Solved these Questions
Similar Questions
Three men or five women can complete a piece of work in 8 days. In how many days can 6 men and 6 women complete it?
View SolutionThe ratio of the rate of work done for a woman and a man is 2:1. Six women can complete a piece of work in 20 days. If 2 women and 6 men work together, then in how many days will they complete the work ?
View Solution
Knowledge Check
20 men or 24 women can complete a piece of work in 20 days. If 30 men and 112 women under take to complete the work, the work will be completed in:
A10 daysB12 daysC15 daysD16 days9 women con complete a piece of work in 19 days. How
many days will 18 women take to complete the same piece of
work ?A12 daysB6.5 daysC9 daysDNone of theseThe ratio of the rate of work done for a woman and a man is 2:1. Six women can complete a piece of work in 20 days. If 2 women and 6 men work together, then in how many days will they complete the work ?
A24B30C20DNone of the above
The ratio of the rate of work done for a woman and a man is 2:1. Six women can complete a piece of work in 20 days. If 2 women and 6 men work together, then in how many days will they complete the work ?
View Solution7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work
View Solution21 men can complete a piece of work in 427 days. In how many days can 18 men complete the same piece of work?
View Solution2 men and 3 women together or 4 men together can complete a piece of work in 20 days.3 men and 3 women will complete the same work in :
View SolutionIf 3 men and 7 women can complete a work in 10 days and 4 men and 6 women need 8 days to complete the same work. In how many days will 10 women complete the same work?
View Solution