Doubtnut Promotions Sticky

If 3 men or 9 boys can finish a work in 21 days . In how many days, can 5 men and 6 boys together do the same work ?

A

12 days

B

8 days

C

14 days

D

None the above

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will first determine the work done by men and boys, and then find out how many days it will take for 5 men and 6 boys to complete the same work.

Step 1: Determine the total work done by men and boys

Given that:
- 3 men can finish the work in 21 days.
- 9 boys can finish the same work in 21 days.

Let's denote:
- The work done by 1 man in 1 day as M (units of work).
- The work done by 1 boy in 1 day as B (units of work).

Total work done by 3 men in 21 days:
Total Work=Work per day×Number of days=3M×21=63M units

Total work done by 9 boys in 21 days:
Total Work=Work per day×Number of days=9B×21=189B units

Since both expressions represent the same total work, we can set them equal to each other:
63M=189B

Step 2: Simplify the equation

Dividing both sides by 63:
M=189B63=3B

This tells us that the work done by one man in one day is equivalent to the work done by three boys in one day.

Step 3: Calculate the total work in terms of k

Let’s express M and B in terms of a common variable k:
- Let B=k (work done by one boy in one day).
- Then M=3k (work done by one man in one day).

Step 4: Find the total work in terms of k

Using either of the earlier equations, we can find the total work:
Total Work=63M=63(3k)=189k units

Step 5: Calculate the work done by 5 men and 6 boys in one day

Now, we need to find out how much work 5 men and 6 boys can do together in one day:
Work done by 5 men=5M=5(3k)=15k
Work done by 6 boys=6B=6k
Total work done by 5 men and 6 boys in one day=15k+6k=21k

Step 6: Calculate the number of days taken by 5 men and 6 boys to complete the work

Let X be the number of days taken to complete the work:
Total Work=Work done in one day×Number of days
189k=21k×X

Dividing both sides by 21k:
X=189k21k=9 days

Conclusion

Thus, 5 men and 6 boys together can complete the work in 9 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    12 men or 24 boys can do a work in 20 days. In how many days, will 24 men and 12 boys together complete the same work ?

    A10
    B12
    C15
    D8
  • Question 2 - Select One

    2 men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 8 days. In how many days can 2 men and 1 boy do the same work ?

    A1212 days
    B1112 days
    C1512 days
    D1312 days
  • Question 3 - Select One

    If 12 men or 20 women can do a work in 54 days, then in how many days can 9 men and 12 women together do the work?

    A38
    B32
    C40
    D35