Doubtnut Promotions Sticky

A contract is to be completed in 92 days and 234 men set to work , each working 16h a day. After 66 days , 4/7 of the work is completed. How many additional men many be employed , so that the work may be completed in time , each man now working 18h a day ?

A

396

B

162

C

200

D

None of these

Video Solution
Text Solution
Verified by Experts

The correct Answer is:A

|
Answer

Step by step video, text & image solution for A contract is to be completed in 92 days and 234 men set to work , each working 16h a day. After 66 days , 4/7 of the work is completed. How many additional men many be employed , so that the work may be completed in time , each man now working 18h a day ? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?

    A60
    B56
    C70
    D42
  • Question 2 - Select One

    A contract to be completed in 46 days and 117 men were set work, each working 8 hours per day. After 33 day, 4/7th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day ?

    A80
    B81
    C84
    D85
  • Question 3 - Select One

    A contract is to be completed in 50 days and 105 men were
    set to work, each working 8 h a day. After 25 days, 2/5 th of
    the work is finished. How many additional men be employed,
    so that the work may be completed on time, each man now
    working 9 h a day?

    A34
    B36
    C35
    D37