Ahluwalia and Bimal together take 6 days to finish the work. Bimal and Jalan together take 10 days to finish the work. What is the difference between number of days taken by Ahluwalia and Jalan when they worked alone to complete the whole work?

A

12 days

B

16 days

C

15 days

D

can't be determined

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem, we need to determine the individual efficiencies of Ahluwalia, Bimal, and Jalan based on the information given. Let's break down the steps:

Step 1: Understand the Work Done Together
Ahluwalia and Bimal together take 6 days to finish the work. We can denote the total work as W. The work done by Ahluwalia and Bimal in one day is:
Work per day (A + B)=W6

Step 2: Work Done by Bimal and Jalan
Bimal and Jalan together take 10 days to finish the work. Therefore, the work done by Bimal and Jalan in one day is:
Work per day (B + J)=W10

Step 3: Set Total Work
To simplify calculations, we can assume the total work W is the least common multiple (LCM) of 6 and 10, which is 30 units.

Step 4: Calculate Daily Work
From our assumptions:
- For Ahluwalia and Bimal:
A+B=306=5 units/day
- For Bimal and Jalan:
B+J=3010=3 units/day

Step 5: Create Equations
Now we have two equations:
1. A+B=5 (Equation 1)
2. B+J=3 (Equation 2)

Step 6: Solve for Individual Efficiencies
From Equation 1, we can express B in terms of A:
B=5A

Substituting this into Equation 2:
(5A)+J=3
J=3(5A)
J=A2

Step 7: Find Days Taken by Each Worker Alone
Now we have:
- B=5A
- J=A2

The number of days taken by each worker alone to complete the whole work can be calculated as follows:
- Days taken by Ahluwalia:
Days by A=WA=30A
- Days taken by Jalan:
Days by J=WJ=30A2

Step 8: Find the Difference
The difference in the number of days taken by Ahluwalia and Jalan is:
Difference=30A30A2

Conclusion
However, since we have two variables (A and J) and only two equations, we cannot determine the exact values of A and J without additional information. Therefore, we cannot find the difference in days taken by Ahluwalia and Jalan.

Final Answer
The difference in the number of days taken by Ahluwalia and Jalan cannot be determined with the given information.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B together finish a work in 4 day while Aalone finishes the work girl 12 day In how many days will B finish the san work ?

    A5
    B6
    C7
    D8
  • A can finish a work in 7 days. B can finish the same work in 9 days. The days required to finish the work by both of them together.

    A11516
    B21516
    C31516
    D41516
  • A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in

    A15 days
    B18 days
    C20 days
    D25 days