Doubtnut Promotions Sticky

A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 13rd of the work was still to be done. How many more men were required to complete the work in stipulated time?

A

16

B

15

C

20

D

25

Video Solution
Text Solution
Verified by Experts

The correct Answer is:C

|
Answer

Step by step video, text & image solution for A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that (1)/(3)rd of the work was still to be done. How many more men were required to complete the work in stipulated time? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    10 men can make a wall in 8 days. How many men required to complete the same work in half day

    A80
    B100
    C120
    D160
  • Question 2 - Select One

    If 15 men can do a work in 48 days, then how many men will be required to complete the work in 30 days ?

    A,21
    B20
    C24
    D22
  • Question 3 - Select One

    A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?

    A20
    B30
    C15
    D45