Doubtnut Promotions Sticky

A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 13rd of the work was still to be done. How many more men were required to complete the work in stipulated time?

A

16

B

15

C

20

D

25

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will follow the reasoning provided in the video transcript.

Step 1: Understand the total work and initial conditions
The contractor has 40 days to complete the work and has deployed 20 men.

Step 2: Calculate the total work done in 32 days
Since he realized 8 days before the scheduled time that 1/3 of the work was still to be done, it means he completed 2/3 of the work in the first 32 days.

Step 3: Determine the amount of work done by 20 men in 32 days
Let the total work be represented as W. The work done in 32 days by 20 men can be calculated as:
Work done=Number of men×Days=20 men×32 days
This means:
23W=20×32
23W=640
To find W, we can rearrange the equation:
W=640×32=960

Step 4: Calculate the remaining work
Since 1/3 of the work is still to be done, we can calculate:
Remaining work=13W=13×960=320

Step 5: Determine the remaining time
There are 8 days left to complete the remaining work.

Step 6: Calculate the number of men needed to complete the remaining work
Let X be the number of additional men required. The total number of men working now will be 20+X. The work done by these men in 8 days should equal the remaining work:
(20+X)×8=320

Step 7: Solve for X
Now we can solve the equation:
20×8+X×8=320
160+8X=320
Subtracting 160 from both sides gives:
8X=160
Dividing both sides by 8 gives:
X=20

Conclusion
The contractor needs to hire 20 more men to complete the work on time.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    10 men can make a wall in 8 days. How many men required to complete the same work in half day

    A80
    B100
    C120
    D160
  • Question 2 - Select One

    If 15 men can do a work in 48 days, then how many men will be required to complete the work in 30 days ?

    A,21
    B20
    C24
    D22
  • Question 3 - Select One

    A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?

    A20
    B30
    C15
    D45