Doubtnut Promotions Sticky

Kaushalya can do a work in 20 days, while Kaikeyi can do the same work in 25 days. They started the work jointly. Few days later Sumitra also joined them and thus all of them completed the whole work in 10 days. All of them were paid total Rs. 700. What is the share of Sumitra?

A

Rs. 130

B

Rs. 185

C

Rs. 70

D

can't be determind

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will calculate the work done by each person and then determine Sumitra's share based on the total payment.

Step 1: Determine the work rates of Kaushalya and Kaikeyi
- Kaushalya can complete the work in 20 days. Therefore, her work rate is:
Work rate of Kaushalya=1 work20 days=120 work/day
- Kaikeyi can complete the work in 25 days. Therefore, her work rate is:
Work rate of Kaikeyi=1 work25 days=125 work/day

Step 2: Find the least common multiple (LCM) of their work durations
- The LCM of 20 and 25 is 100. We will consider the total work to be 100 units.

Step 3: Calculate the daily work done by each person in terms of units
- Kaushalya's daily work in units:
Daily work of Kaushalya=100 units20 days=5 units/day
- Kaikeyi's daily work in units:
Daily work of Kaikeyi=100 units25 days=4 units/day

Step 4: Calculate the total work done by Kaushalya and Kaikeyi in 10 days
- Total work done by Kaushalya in 10 days:
Work by Kaushalya=5 units/day×10 days=50 units
- Total work done by Kaikeyi in 10 days:
Work by Kaikeyi=4 units/day×10 days=40 units

Step 5: Calculate the total work done by both and the remaining work
- Total work done by both:
Total work done by Kaushalya and Kaikeyi=50+40=90 units
- Remaining work to be completed by Sumitra:
Remaining work=10090=10 units

Step 6: Calculate the share of Sumitra based on the total payment
- The total payment for the work is Rs. 700. Since 100 units of work corresponds to Rs. 700, the value of 1 unit of work is:
Value of 1 unit=700100=7 Rs/unit
- Sumitra's share based on the 10 units of work she completed:
Share of Sumitra=10 units×7 Rs/unit=70 Rs

Final Answer
Sumitra's share is Rs. 70.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a work in 20 days, while B can do the same work in 25 days. They started the work jointly. Few days later C also joined them and thus all of them completed the whole work in 10 days. All of them were paid total of rs 700. What is the share of C?
    A किसी कार्य को 20 दिनों में कर सकता है जबकि B इसी कार्य को 25 दिनों में कर सकता है | उन्होंने एक साथ इस कार्य को शुरू किया | कुछ दिनों बाद C उनके साथ शामिल हो गया और इस प्रकार उन सभी ने इस पूरे कार्य को 10 दिनों में पूरा किया | उन सभी को कुल 700 रुपये का भुगतान किया गया |C का हिस्सा क्या है ?

    A₹ 130
    B₹ 185
    C₹ 70
    Dcan’t be determined
  • Question 2 - Select One

    If 10 men can do a work in 20 days, then how many men can do the same work in 4 days?
    (a)60 men
    (b)20 men
    (c)50 men
    (d)40 men

    A60 men
    B20 men
    C50 men
    D40 men
  • Question 3 - Select One

    A can do a work in 5 days while B can do the same work in 8 days. They worked together to complete the work and earned Rs. 6760. Find A's share ?

    ARs. 5070
    BRs. 3600
    CRs. 4160
    DRs. 4056