Doubtnut Promotions Sticky

A can do a work in 20 days, while B can do the same work in 25 days. They started the work jointly. Few days later C also joined them and thus all of them completed the whole work in 10 days. All of them were paid total of rs 700. What is the share of C?
A किसी कार्य को 20 दिनों में कर सकता है जबकि B इसी कार्य को 25 दिनों में कर सकता है | उन्होंने एक साथ इस कार्य को शुरू किया | कुछ दिनों बाद C उनके साथ शामिल हो गया और इस प्रकार उन सभी ने इस पूरे कार्य को 10 दिनों में पूरा किया | उन सभी को कुल 700 रुपये का भुगतान किया गया |C का हिस्सा क्या है ?

A

a) 55

B

b) 65

C

c) 75

D

d) 70

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will calculate the work done by A, B, and C, and then determine C's share of the payment based on their contributions.

Step 1: Determine the work rates of A and B
- A can complete the work in 20 days. Therefore, A's work rate is:
Work rate of A=120 work/day

- B can complete the work in 25 days. Therefore, B's work rate is:
Work rate of B=125 work/day

Step 2: Find the least common multiple (LCM) of their work times
- The LCM of 20 and 25 is 100. This means we can consider the total work as 100 units.

Step 3: Calculate the efficiencies of A and B
- A's efficiency (work done per day) is:
Efficiency of A=10020=5 units/day

- B's efficiency (work done per day) is:
Efficiency of B=10025=4 units/day

Step 4: Calculate the total efficiency of A and B
- The combined efficiency of A and B is:
Total efficiency of A and B=5+4=9 units/day

Step 5: Determine the total work done in 10 days
- Since A and B started the work together and completed it in 10 days, the total work done is:
Total work done in 10 days=Total efficiency×Number of days=9×10=90 units

Step 6: Calculate the remaining work and C's contribution
- The total work is 100 units, and A and B together completed 90 units. Therefore, the remaining work that C completed is:
Work done by C=10090=10 units

Step 7: Calculate C's efficiency
- Since C worked with A and B for the remaining 10 units, we need to find out how many days C worked. Assuming C joined after some days, we can say:
- Let x be the number of days A and B worked alone.
- Then, 10x is the number of days all three worked together.

However, since we know they completed the work in 10 days, we can assume C worked the entire duration of 10 days.

Step 8: Calculate the share of each worker based on their efficiencies
- The total efficiency of all three (A, B, and C) is:
Total efficiency=5+4+1=10 units/day

- The share of each worker in the total payment of Rs 700 is based on their efficiency:
- A's share:
Share of A=510×700=350 Rs

- B's share:
Share of B=410×700=280 Rs

- C's share:
Share of C=110×700=70 Rs

Final Answer
- C's share is Rs 70.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a work in 20 days, while B can do the same work in 25 days. They started the work jointly. Few days later C also joined them and thus all of them completed the whole work in 10 days. All of them were paid total of rs 700. What is the share of C?
    A किसी कार्य को 20 दिनों में कर सकता है जबकि B इसी कार्य को 25 दिनों में कर सकता है | उन्होंने एक साथ इस कार्य को शुरू किया | कुछ दिनों बाद C उनके साथ शामिल हो गया और इस प्रकार उन सभी ने इस पूरे कार्य को 10 दिनों में पूरा किया | उन सभी को कुल 700 रुपये का भुगतान किया गया |C का हिस्सा क्या है ?

    A₹ 130
    B₹ 185
    C₹ 70
    Dcan’t be determined
  • Question 2 - Select One

    Kaushalya can do a work in 20 days, while Kaikeyi can do the same work in 25 days. They started the work jointly. Few days later Sumitra also joined them and thus all of them completed the whole work in 10 days. All of them were paid total Rs. 700. What is the share of Sumitra?

    ARs. 130
    BRs. 185
    CRs. 70
    Dcan't be determind
  • Question 3 - Select One

    A can complete a work in 20 days and B can complete the same work in 25 days . If both of them work together, in 3 days what per cant of the total work will be completed ?

    A9
    B12
    C25
    D27