How many days are there in x weeks x days? 7x2 (b) 8x (c) 14x (d) 7
To solve the question "How many days are there in x weeks and x days?", we can follow these steps:
Step 1: Understand the number of days in a week
We know that 1 week consists of 7 days.
Step 2: Calculate the number of days in x weeks
If we have x weeks, the total number of days in those weeks can be calculated as:
\(
\text{Days in } x \text{ weeks} = 7 \times x = 7x
\)
Step 3: Add the additional days
In addition to the days from the weeks, we also have x additional days. Therefore, we need to add these days to the total number of days calculated in Step 2:
\(
\text{Total days} = \text{Days in } x \text{ weeks} + \text{Additional days} = 7x + x
\)
Step 4: Simplify the expression
Now, we simplify the expression:
\(
7x + x = 8x
\)
Conclusion
Thus, the total number of days in x weeks and x days is:
\(
\text{Total days} = 8x
\)
Final Answer
The correct answer is (b) 8x.
---
We know that 1 week consists of 7 days.
If we have x weeks, the total number of days in those weeks can be calculated as:
\(
\text{Days in } x \text{ weeks} = 7 \times x = 7x
\)
In addition to the days from the weeks, we also have x additional days. Therefore, we need to add these days to the total number of days calculated in Step 2:
\(
\text{Total days} = \text{Days in } x \text{ weeks} + \text{Additional days} = 7x + x
\)
Now, we simplify the expression:
\(
7x + x = 8x
\)
Thus, the total number of days in x weeks and x days is:
\(
\text{Total days} = 8x
\)
The correct answer is (b) 8x.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
X and Y can do a piece of work in 72 days. Y and Z can do it in 120 days. X and Z can do it in 90 days. In how many days all the three together can do the work ?
A)100 days
B)150 days
C)60 days
D) 80 daysA100 daysB150 daysC60 daysD80 days - Question 2 - Select One
X can do a piece of work in 6 days while Y can do the same work in 8 days. Find in how many days X and Y together can do the same work?
The following are the steps involved in solving the above problem. Arrange them in sequential order.
One day's work of X is 1/6 one day's work of Y is 1/8
X can do a piece of work in 6 days and Y can do the same work in 8 days.
X and Y together can do the same work in 337 days.
One day's work of X and Y=724AABCDBBADCCBDACDABDC
10 cows can graze in a field for 15 days and 20 cows can graze in the same field for 10 days. For how many days can 30 cows graze in the field? (a) 5 days (b) 712 days (c) 723 days (d) 813 days
View SolutionIf x men, working x hours per day, can do x units of work in x days, then y mens, working y hours per day would be able to complete how many units of work in y days? x2y3 b. x3y2 c. x3y2 d. y3x2
View SolutionThe initial count of bacteria is x and it becomes y times every day. The total count of backteria after one week is 7 xy (b) x+7y (c) xy7 (d) xy6
View SolutionHow many solutions does the equation8x+27x12x+18x = 76have? (A) Exactly one (B) Exactly two (C) Finitely many (D) Infinitely many
View SolutionIf 8tanx=15 , then sinx−cosx is equal to
View SolutionIf the mean of 6, 7, x, 8, y, 14 is 9, then (a) x+y=21 (b) x+y=19 (c) x−y=19 (d) x−y=21
View Solution