If x men, working x hours per day, can do x units of work in x days, then y mens, working y hours per day would be able to complete how many units of work in y days? x2y3 b. x3y2 c. x3y2 d. y3x2
To solve the problem, we need to analyze the work done by the men based on the given information.
Step 1: Understand the work done by x men
If x men can do x units of work in x days while working x hours per day, we can calculate the total work done in terms of man-hours.
- Total man-hours = Number of men × Hours per day × Days
- Total man-hours = x men × x hours/day × x days = x3 man-hours
Since they complete x units of work in x3 man-hours, the work done per man-hour is:
- Work done per man-hour = Total work / Total man-hours = xx3=1x2 units of work per man-hour.
Step 2: Calculate work done by y men
Now, we need to find out how much work y men can do in y days while working y hours per day.
- Total man-hours for y men = y men × y hours/day × y days = y3 man-hours.
Step 3: Calculate total work done by y men
Using the work done per man-hour we calculated earlier:
- Total work done by y men = Work done per man-hour × Total man-hours
- Total work done by y men = (1x2)×y3
Step 4: Simplify the expression
Now, we can express the total work done by y men in terms of x and y:
- Total work done = y3x2 units.
Step 5: Identify the correct option
Now we need to check which option matches our result:
- The calculated total work done is y3x2.
The correct answer is option d. (y^3)/(x^2).
---
If x men can do x units of work in x days while working x hours per day, we can calculate the total work done in terms of man-hours.
- Total man-hours = x men × x hours/day × x days = x3 man-hours
- Work done per man-hour = Total work / Total man-hours = xx3=1x2 units of work per man-hour.
Now, we need to find out how much work y men can do in y days while working y hours per day.
Using the work done per man-hour we calculated earlier:
- Total work done by y men = Work done per man-hour × Total man-hours
- Total work done by y men = (1x2)×y3
Now, we can express the total work done by y men in terms of x and y:
- Total work done = y3x2 units.
Now we need to check which option matches our result:
- The calculated total work done is y3x2.
Topper's Solved these Questions
Similar Questions
If x men working x hours per day can do x units of work in x days, then y men working y hours per day in y days would be able to do k units of work. What is the value of k ?
View Solution4 men, each working 6 hours per day can build a wall in 9 days. How long will 6 men, each working 3 hours per day take to finish the same work?
View Solution
Knowledge Check
- Question 1 - Select One
If x men, working x hours per day, can do x units of work in x days, then y mens, working y hours per day would be able to complete how many units of work in y days? x2y3 b. x3y2 c. x3y2 d. y3x2
Ax2y3 units of workBx3y2 units of workCy2x3 units of workDy3x2 units of work - Question 2 - Select One
If m men working m hr per day, can do m units of work in m days, then n men working n hr per day would be able to complete how many units of work in n days?
An3m2Bm3n2Cm4n2Dn4m2 - Question 3 - Select One
If 10 men working for 6 hours per day can complete a piece of work in 90 days, in how many days will 6 men working for 15 hours per day complete the same piece of work ?
A30 daysB20 daysC60 daysD40 days
If M1 men can do W1 work in D1 days working H1 hours per day and M2 men can do W2 work in D2 days working H2 hours per day then
View SolutionIf 28 men working 8 hours per day can finish a piece of work in 10 days. How many hours per day 40 men must work to complete the same work in 8 days.
View SolutionIf 16 men working 12 hours a day can complete a work in 27 days, then working for how many hours a day can 18 men complete the work in 24 days ?
यदि 16 पुरुष प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 27 दिनों में पूरा करते हैं, तो इस कार्य को 24 दिनों में पूरा करने के लिए 18 पुरुषों को दिन में कितने घंटे कार्य करना पड़ेगा ?View SolutionMohan can complete his work in 3 days by doing 2 hours per day. How much work can be complete in one day ?
View Solution8 men working for 9 hours a day can complete a piece of work in 20 days. In how many days can 7 men working for 10 hours a day complete the same piece of work?
View Solution