If x men, working x hours per day, can do x units of work in x days, then y mens, working y hours per day would be able to complete how many units of work in y days? x2y3 b. x3y2 c. x3y2 d. y3x2

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we need to analyze the work done by the men based on the given information.

Step 1: Understand the work done by x men
If x men can do x units of work in x days while working x hours per day, we can calculate the total work done in terms of man-hours.

- Total man-hours = Number of men × Hours per day × Days
- Total man-hours = x men × x hours/day × x days = x3 man-hours

Since they complete x units of work in x3 man-hours, the work done per man-hour is:
- Work done per man-hour = Total work / Total man-hours = xx3=1x2 units of work per man-hour.

Step 2: Calculate work done by y men
Now, we need to find out how much work y men can do in y days while working y hours per day.

- Total man-hours for y men = y men × y hours/day × y days = y3 man-hours.

Step 3: Calculate total work done by y men
Using the work done per man-hour we calculated earlier:
- Total work done by y men = Work done per man-hour × Total man-hours
- Total work done by y men = (1x2)×y3

Step 4: Simplify the expression
Now, we can express the total work done by y men in terms of x and y:
- Total work done = y3x2 units.

Step 5: Identify the correct option
Now we need to check which option matches our result:
- The calculated total work done is y3x2.

The correct answer is option d. (y^3)/(x^2).

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If x men, working x hours per day, can do x units of work in x days, then y mens, working y hours per day would be able to complete how many units of work in y days? x2y3 b. x3y2 c. x3y2 d. y3x2

    Ax2y3 units of work
    Bx3y2 units of work
    Cy2x3 units of work
    Dy3x2 units of work
  • If m men working m hr per day, can do m units of work in m days, then n men working n hr per day would be able to complete how many units of work in n days?

    An3m2
    Bm3n2
    Cm4n2
    Dn4m2
  • If 10 men working for 6 hours per day can complete a piece of work in 90 days, in how many days will 6 men working for 15 hours per day complete the same piece of work ?

    A30 days
    B20 days
    C60 days
    D40 days