A is 50% as efficient as B. C does half of the work done by A and B together. If C alone does the work in 20 days, then A, B and C together can do the work in
523 days
623 days
6 days
7 days
The correct Answer is:B
To solve the problem step by step, let's break it down:
Step 1: Define the efficiency of A and B
Let B's efficiency be represented as 1 unit of work per day. Since A is 50% as efficient as B, A's efficiency will be:
Efficiency of A=0.5×Efficiency of B=0.5×1=0.5 units of work per day
Step 2: Calculate the combined efficiency of A and B
The combined efficiency of A and B together is:
Efficiency of A + B=Efficiency of A+Efficiency of B=0.5+1=1.5 units of work per day
Step 3: Determine C's efficiency
According to the problem, C does half of the work done by A and B together. Therefore, C's efficiency is:
Efficiency of C=12×Efficiency of (A + B)=12×1.5=0.75 units of work per day
Step 4: Calculate the total work done by C in 20 days
If C alone can complete the work in 20 days, the total work can be expressed as:
Total Work=Efficiency of C×Time taken by C=0.75×20=15 units of work
Step 5: Calculate the total efficiency of A, B, and C together
Now, we need to find the combined efficiency of A, B, and C:
Efficiency of (A + B + C)=Efficiency of A+Efficiency of B+Efficiency of C=0.5+1+0.75=2.25 units of work per day
Step 6: Calculate the time taken by A, B, and C together to complete the work
To find out how many days it will take for A, B, and C to complete the total work of 15 units, we use the formula:
Time=Total WorkCombined Efficiency=152.25
Calculating this gives:
Time=152.25=15×100225=1500225=609=203 days
Final Answer
Thus, A, B, and C together can complete the work in:
203 days or 623 days
Let B's efficiency be represented as 1 unit of work per day. Since A is 50% as efficient as B, A's efficiency will be:
Efficiency of A=0.5×Efficiency of B=0.5×1=0.5 units of work per day
The combined efficiency of A and B together is:
Efficiency of A + B=Efficiency of A+Efficiency of B=0.5+1=1.5 units of work per day
According to the problem, C does half of the work done by A and B together. Therefore, C's efficiency is:
Efficiency of C=12×Efficiency of (A + B)=12×1.5=0.75 units of work per day
If C alone can complete the work in 20 days, the total work can be expressed as:
Total Work=Efficiency of C×Time taken by C=0.75×20=15 units of work
Now, we need to find the combined efficiency of A, B, and C:
Efficiency of (A + B + C)=Efficiency of A+Efficiency of B+Efficiency of C=0.5+1+0.75=2.25 units of work per day
To find out how many days it will take for A, B, and C to complete the total work of 15 units, we use the formula:
Time=Total WorkCombined Efficiency=152.25
Calculating this gives:
Time=152.25=15×100225=1500225=609=203 days
Thus, A, B, and C together can complete the work in:
203 days or 623 days
Similar Questions
A is 50% as efficient as B.C does half of the work done by A and B together. If C alone does the work in 40 days, then A, B and C together can do the work in: 1313days b. 15 days c. 20 days d. 30 days
View SolutionA does half as much work as B and C does half as much work as A and B together. If C alone can finish the work in 40 days, then all together will finish the work in?
View Solution
Knowledge Check
- Question 1 - Select One
A does half as much work as B and C does half as much work as A and B together. If C alone can finish the work in 40 days, then all together will finish the work in?
A523 daysB623 daysC6 daysD7 days - Question 2 - Select One
A and B together can do a work in 10 days. B and C together can do the same work in 6 days. A and C together can do the work in 12 days. Then A, B and C together can do the work in
A28 daysB14 daysC5 57 daysD8 27 days - Question 3 - Select One
If A is twice as efficient as B, and A and B together can complete a work in 20 days, then find the number of days in which B can do the work alone.
(a)60 days
(b) 50 days
(c)30 days
(d)40 daysA60 daysB50 daysC30 daysD40 days
A does half as much work as B, and C does half as much work as A and B together. If C alone can finish the work in 40 days, then all together will finish the work in (B) 15 days (A) 13(13) days (D) 30 days (C) 20 days
View SolutionA and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.
View SolutionA and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.
View SolutionA and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.
View SolutionA takes as much time as B and C together to complete a work. While A and B together can do this piece of work in 10 days. C alone can do this piece of work in 50 days. In how many days will this work be completed by B alone?
View Solution