Doubtnut Promotions Sticky

A is 50% as efficient as B. C does half of the work done by A and B together. If C alone does the work in 20 days, then A, B and C together can do the work in

A

523 days

B

623 days

C

6 days

D

7 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, let's break it down:

Step 1: Define the efficiency of A and B
Let B's efficiency be represented as 1 unit of work per day. Since A is 50% as efficient as B, A's efficiency will be:
Efficiency of A=0.5×Efficiency of B=0.5×1=0.5 units of work per day

Step 2: Calculate the combined efficiency of A and B
The combined efficiency of A and B together is:
Efficiency of A + B=Efficiency of A+Efficiency of B=0.5+1=1.5 units of work per day

Step 3: Determine C's efficiency
According to the problem, C does half of the work done by A and B together. Therefore, C's efficiency is:
Efficiency of C=12×Efficiency of (A + B)=12×1.5=0.75 units of work per day

Step 4: Calculate the total work done by C in 20 days
If C alone can complete the work in 20 days, the total work can be expressed as:
Total Work=Efficiency of C×Time taken by C=0.75×20=15 units of work

Step 5: Calculate the total efficiency of A, B, and C together
Now, we need to find the combined efficiency of A, B, and C:
Efficiency of (A + B + C)=Efficiency of A+Efficiency of B+Efficiency of C=0.5+1+0.75=2.25 units of work per day

Step 6: Calculate the time taken by A, B, and C together to complete the work
To find out how many days it will take for A, B, and C to complete the total work of 15 units, we use the formula:
Time=Total WorkCombined Efficiency=152.25
Calculating this gives:
Time=152.25=15×100225=1500225=609=203 days

Final Answer
Thus, A, B, and C together can complete the work in:
203 days or 623 days

|
Updated on:7/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A does half as much work as B and C does half as much work as A and B together. If C alone can finish the work in 40 days, then all together will finish the work in?

    A523 days
    B623 days
    C6 days
    D7 days
  • Question 2 - Select One

    A and B together can do a work in 10 days. B and C together can do the same work in 6 days. A and C together can do the work in 12 days. Then A, B and C together can do the work in

    A28 days
    B14 days
    C5 57 days
    D8 27 days
  • Question 3 - Select One

    If A is twice as efficient as B, and A and B together can complete a work in 20 days, then find the number of days in which B can do the work alone.
    (a)60 days
    (b) 50 days
    (c)30 days
    (d)40 days

    A60 days
    B50 days
    C30 days
    D40 days