A does half as much work as B and C does half as much work as A and B together. If C alone can finish the work in 40 days, then all together will finish the work in?
The correct Answer is:1313 day
To solve the problem step by step, let's break down the information given and find the total time taken for A, B, and C to complete the work together.
Step 1: Define the work done by A, B, and C
- Let the work done by B in one day be x.
- Since A does half as much work as B, the work done by A in one day is x2.
- C does half as much work as A and B together. The work done by A and B together is x2+x=3x2. Therefore, the work done by C in one day is 12×3x2=3x4.
Step 2: Determine C's total work
- We know that C alone can finish the work in 40 days. This means the total work can be calculated as:
Total Work=C's work per day×Number of days
Total Work=3x4×40=30x
Step 3: Calculate the total work done by A, B, and C together
- Now, we will find the total work done by A, B, and C in one day.
- The total work done by A, B, and C together is:
Total Work per day=A+B+C=x2+x+3x4
- To add these, we need a common denominator. The common denominator for 2, 1, and 4 is 4.
=2x4+4x4+3x4=2x+4x+3x4=9x4
Step 4: Calculate the time taken for A, B, and C to finish the work together
- We know the total work is 30x and the work done together in one day is 9x4.
- The time taken to complete the work together is:
Time=Total WorkTotal Work per day=30x9x4=30x×49x=1209=403 days
Final Answer
Thus, A, B, and C together will finish the work in 403 days, which is approximately 13.33 days.
- Let the work done by B in one day be x.
- Since A does half as much work as B, the work done by A in one day is x2.
- C does half as much work as A and B together. The work done by A and B together is x2+x=3x2. Therefore, the work done by C in one day is 12×3x2=3x4.
- We know that C alone can finish the work in 40 days. This means the total work can be calculated as:
Total Work=C's work per day×Number of days
Total Work=3x4×40=30x
- Now, we will find the total work done by A, B, and C in one day.
- The total work done by A, B, and C together is:
Total Work per day=A+B+C=x2+x+3x4
- To add these, we need a common denominator. The common denominator for 2, 1, and 4 is 4.
=2x4+4x4+3x4=2x+4x+3x4=9x4
- We know the total work is 30x and the work done together in one day is 9x4.
- The time taken to complete the work together is:
Time=Total WorkTotal Work per day=30x9x4=30x×49x=1209=403 days
Thus, A, B, and C together will finish the work in 403 days, which is approximately 13.33 days.
Topper's Solved these Questions
Similar Questions
By working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?
View SolutionBy working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?
View Solution
Knowledge Check
- Question 1 - Select One
A is 50% as efficient as B. C does half of the work done by A and B together. If C alone does the work in 20 days, then A, B and C together can do the work in
A523 daysB623 daysC6 daysD7 days - Question 2 - Select One
A does half as much work as B and C does half as much work as A and B together. If C alone can finish the work in 40 days, then all together will finish the work in?
A523 daysB623 daysC6 daysD7 days - Question 3 - Select One
A can do one and a half as much of a work which B can do in one day. B alone can do a piece of work in 18 days. They together can finish that work in
A1015 daysB1115 daysC515 daysD715 days
A can finish 80% of work done by B in 20% more time taken by B. Working together they can finish the work in 40 days. In how many days they will finish the work working alone?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 18 days. In how many days will A alone finish the work?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work?
View SolutionA can do a piece of work in 60 days. He works for 15 days and then B alone finishes the remaining work in 30 days. The two together can finish the work in
View SolutionA is twice as fast a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work ?
View Solution