A and B together can do a work in 10 days. B and C together can do the same work in 6 days. A and C together can do the work in 12 days. Then A, B and C together can do the work in
28 days
14 days
5 57 days
8 27 days
The correct Answer is:C
To solve the problem step by step, we will first determine the work rates of A, B, and C based on the information provided.
Step 1: Determine the work rates of A, B, and C
1. Work done by A and B together in 10 days:
- Work rate of A and B together = 1/10 (since they complete the work in 10 days).
2. Work done by B and C together in 6 days:
- Work rate of B and C together = 1/6 (since they complete the work in 6 days).
3. Work done by A and C together in 12 days:
- Work rate of A and C together = 1/12 (since they complete the work in 12 days).
Step 2: Set up equations based on the work rates
Let:
- Rate of A = a (work done by A in one day)
- Rate of B = b (work done by B in one day)
- Rate of C = c (work done by C in one day)
From the information:
1. a+b=110 (Equation 1)
2. b+c=16 (Equation 2)
3. a+c=112 (Equation 3)
Step 3: Solve the equations
To find the individual work rates, we can manipulate these equations.
Step 3.1: Add all three equations
(a+b)+(b+c)+(a+c)=110+16+112
This simplifies to:
2a+2b+2c=110+16+112
Step 3.2: Find a common denominator for the right side
The least common multiple of 10, 6, and 12 is 60. Therefore:
110=660,16=1060,112=560
Adding these gives:
6+10+560=2160=720
So, we have:
2a+2b+2c=720
Dividing by 2:
a+b+c=740(Equation4)
Step 4: Calculate the combined work rate of A, B, and C
The combined work rate of A, B, and C is:
a+b+c=740
This means A, B, and C together can complete 740 of the work in one day.
Step 5: Calculate the time taken by A, B, and C to complete the work
To find the number of days taken to complete the work, we take the reciprocal of the combined work rate:
Days=1a+b+c=1740=407 days
Final Answer
A, B, and C together can complete the work in 407 days, which is approximately 5.71 days.
---
1. Work done by A and B together in 10 days:
- Work rate of A and B together = 1/10 (since they complete the work in 10 days).
- Work rate of B and C together = 1/6 (since they complete the work in 6 days).
- Work rate of A and C together = 1/12 (since they complete the work in 12 days).
Let:
- Rate of A = a (work done by A in one day)
- Rate of B = b (work done by B in one day)
- Rate of C = c (work done by C in one day)
1. a+b=110 (Equation 1)
2. b+c=16 (Equation 2)
3. a+c=112 (Equation 3)
To find the individual work rates, we can manipulate these equations.
(a+b)+(b+c)+(a+c)=110+16+112
This simplifies to:
2a+2b+2c=110+16+112
The least common multiple of 10, 6, and 12 is 60. Therefore:
110=660,16=1060,112=560
Adding these gives:
6+10+560=2160=720
So, we have:
2a+2b+2c=720
Dividing by 2:
a+b+c=740(Equation4)
The combined work rate of A, B, and C is:
a+b+c=740
This means A, B, and C together can complete 740 of the work in one day.
To find the number of days taken to complete the work, we take the reciprocal of the combined work rate:
Days=1a+b+c=1740=407 days
A, B, and C together can complete the work in 407 days, which is approximately 5.71 days.
Similar Questions
A and B together can do a piece of work in 36 days, B and C together can do it in 24 days. A and C together can do it in 18 days. The three working together can finish the work in
View SolutionA and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.
View Solution
Knowledge Check
- Question 1 - Select One
A and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is
A4 daysB9 daysC8 daysD5 days - Question 2 - Select One
A and B can do a work in 12 days, Band C can do the same work in 15 days, C and A can do the same work in 20 days. The time taken by A, B and C to do the same work is
A5 daysB10 daysC15 daysD20 days - Question 3 - Select One
A can do a work in 20 days and B can do the same work in 30 days in how many days canA and B together do the work?
A15B16C10D12
A and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.
View SolutionA and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.
View SolutionA and B together can do a piece of work in 12 days. While B and C together can do a piece of work in 8 days. C and A together can do a piece of work in 6 days. In how many days will this work be completed by B alone?
View SolutionA can do a work in 40 days and B can do the same work in 60 days. In how many days they can do it together?
View SolutionA and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. Together they will complete the work in:
View Solution