X and Y can do a piece of work in 30 days. They work together for 6 days and thenX quits and Y finishes the work in 32 days . In how many days can Y do the piece of work alone ?
30 days
32 days
34 days
40 days
The correct Answer is:D
To solve the problem, we need to determine how many days Y can complete the work alone. Let's break down the solution step by step.
Step 1: Determine the work done by X and Y together
Given that X and Y can complete the work together in 30 days, we can express their combined work rate as:
Work done in 1 day by X and Y=130 of the total work (W)
Let the work done by X in one day be x and the work done by Y in one day be y. Therefore, we have:
x+y=W30(1)
Step 2: Calculate the work done in 6 days
When X and Y work together for 6 days, the amount of work they complete is:
Work done in 6 days=6(x+y)=6⋅W30=W5(2)
Step 3: Determine the remaining work after 6 days
After working together for 6 days, the remaining work is:
Remaining work=W−W5=4W5(3)
Step 4: Calculate the work done by Y alone
After 6 days, X quits, and Y completes the remaining work in 32 days. The work done by Y in 32 days is:
Work done by Y in 32 days=32y
Since this work equals the remaining work, we have:
32y=4W5(4)
Step 5: Relate Y's work rate to the total work
From equation (4), we can express y in terms of W:
y=4W5⋅32=W40(5)
Step 6: Substitute y back into equation (1)
Now we substitute y from equation (5) into equation (1):
x+W40=W30
To solve for x, we need a common denominator. The least common multiple of 30 and 40 is 120. Thus, we rewrite the equation:
x+3W120=4W120
Subtracting 3W120 from both sides gives:
x=4W120−3W120=W120(6)
Step 7: Find the total work in terms of Y's work rate
Now we know both x and y:
- x=W120
- y=W40
Step 8: Determine how many days Y takes to complete the work alone
Let d be the number of days Y takes to complete the work alone. Then:
d⋅y=W
Substituting y from equation (5):
d⋅W40=W
Dividing both sides by W (assuming W≠0):
d40=1⟹d=40
Final Answer
Y can complete the piece of work alone in 40 days.
---
Given that X and Y can complete the work together in 30 days, we can express their combined work rate as:
Work done in 1 day by X and Y=130 of the total work (W)
Let the work done by X in one day be x and the work done by Y in one day be y. Therefore, we have:
x+y=W30(1)
When X and Y work together for 6 days, the amount of work they complete is:
Work done in 6 days=6(x+y)=6⋅W30=W5(2)
After working together for 6 days, the remaining work is:
Remaining work=W−W5=4W5(3)
After 6 days, X quits, and Y completes the remaining work in 32 days. The work done by Y in 32 days is:
Work done by Y in 32 days=32y
Since this work equals the remaining work, we have:
32y=4W5(4)
From equation (4), we can express y in terms of W:
y=4W5⋅32=W40(5)
Now we substitute y from equation (5) into equation (1):
x+W40=W30
To solve for x, we need a common denominator. The least common multiple of 30 and 40 is 120. Thus, we rewrite the equation:
x+3W120=4W120
Subtracting 3W120 from both sides gives:
x=4W120−3W120=W120(6)
Now we know both x and y:
- x=W120
- y=W40
Let d be the number of days Y takes to complete the work alone. Then:
d⋅y=W
Substituting y from equation (5):
d⋅W40=W
Dividing both sides by W (assuming W≠0):
d40=1⟹d=40
Y can complete the piece of work alone in 40 days.
Similar Questions
A can do a piece of work in 60 days. He works for 15 days and then B alone finishes the remaining work in 30 days. The two together can finish the work in
View SolutionS can do a piece of work in 80 days and T in 60 days. With the help of U, they finish the work in 20 days. In how many days U alone can do the same work?
View Solution
Knowledge Check
- Question 1 - Select One
Vaibhav can do a piece of work in 60 days. He works there for 15 days and then Sandeep alone finishes the remaining work in 30 days. In how many days will Vaibhav and Sandeep working together finish the work?
A20 daysB24 daysC18 daysD22 days - Question 2 - Select One
S can do a piece of work in 80 days and T in 60 days. With the help of U, they finish the work in 20 days. In how many days U alone can do the same work?
A40B60C48D80 - Question 3 - Select One
A can do a piece of work in 5 days, B can do it in 10 days. With the help of C, they finish the work in 2 days. In how many days C alone can do the whole work?
A3B4C5D6
A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :
View SolutionA can do a piece of work in 12 days and B in 15 days. With help of C, they finish the work in 4 days. In how many days C alone can do the same work?
View SolutionP can do a piece of work in 15 days and Q in 20 days. With help of R, they finish the work in 5 days. In how many days R alone can do the same work?
View SolutionA can do a piece of work in 6 days. B can do it in 9 days. With the assistance of C they completed the work in 3 days. In how many days can C alone do the work? /
A 6 दिनों में एक काम कर सकता है। B इसे 9 दिनों में कर सकता हैं। C की सहायता से उन्होंने 3 दिनों में काम पूरा कर लिया। तो C अकेले कितने दिनों में यह काम करेगा?View SolutionA can do a piece of work in 30 days. He worked for 6 days and B finished the remaining work in 48 days. B alone can do the whole work in how many days?
View Solution