Doubtnut Promotions Sticky

S can do a piece of work in 80 days and T in 60 days. With the help of U, they finish the work in 20 days. In how many days U alone can do the same work?

A

40

B

60

C

48

D

80

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will first determine the work done by S, T, and U, and then find out how long U alone would take to complete the work.

Step 1: Determine the work done by S and T

- S can complete the work in 80 days.
- T can complete the work in 60 days.

To find the work done by each in one day, we can use the formula:
Work done in one day=1Number of days to complete the work

- Work done by S in one day:
Work by S=180 of the work

- Work done by T in one day:
Work by T=160 of the work

Step 2: Calculate the combined work done by S and T in one day

To find the combined work done by S and T in one day, we add the work done by both:
Combined work by S and T=180+160

To add these fractions, we need a common denominator. The least common multiple (LCM) of 80 and 60 is 240.

Converting the fractions:
180=3240and160=4240

Now, adding these:
Combined work by S and T=3240+4240=7240

Step 3: Determine the total work done by S, T, and U together

We know that S, T, and U together finish the work in 20 days. Therefore, the work done by all three in one day is:
Combined work by S, T, and U=120

Step 4: Set up the equation to find U's work

Now, we can set up the equation:
Work by S+Work by T+Work by U=Combined work by S, T, and U
Substituting the values we found:
7240+Work by U=120

Step 5: Convert 120 to a fraction with a denominator of 240

To solve for U's work, we convert 120 to have a denominator of 240:
120=12240

Step 6: Solve for U's work

Now we substitute this back into the equation:
7240+Work by U=12240
Subtract 7240 from both sides:
Work by U=122407240=5240

Step 7: Determine how many days U alone would take to complete the work

Since U does 5240 of the work in one day, we can find out how many days U would take to complete the entire work:
Days taken by U=2405=48 days

Final Answer
U alone can complete the work in 48 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    S can do a piece of work in 80 days and T in 60 days. With the help of U, they finish the work in 20 days. In how many days U alone can do the same work?

    A40
    B60
    C48
    D80
  • Question 2 - Select One

    S can do a piece of work in 80 days and T in 60 days. With the help of U, they finish the work in 20 days. In how many days U alone can do the same work?

    A40
    B60
    C48
    D80
  • Question 3 - Select One

    P can do a piece of work in 15 days and Q in 20 days. With help of R, they finish the work in 5 days. In how many days R alone can do the same work?

    A10
    B12
    C15
    D18